Water, Sewage & Effluent March April 2019 | Page 20

for successful completion. Unfathomably, within a few months and by ‘final design’ stage, the proposed scope of work and cost had escalated to unacceptable levels and, according to the consulting engineers: “Due to funding constraints, the project will be approached in two (2) separate phases of treatment capacity 1ML/day each. Funds available for phase one of the proposed upgrade will be dedicated to the construction of key components to satisfy the original proposal submitted by Rhodes University”; and “The detailed project cost is estimated at R60 016 251.23 (incl. VAT, Contractor P&G, 10% contingencies, professional fees and additional services).” The overall project objective was to upgrade treatment capacity to 2ML/d by converting the current conventional oxidation pond system to an IAPS, and to demonstrate the robustness and sustainable characteristics of IAPS to create a viable platform to launch sustainable food security and job creation. Details of the proposed system are illustrated below, while the measurable deliverables were to: • Increase municipal WWT capacity by up to 12 500 PE; • Produce water suitable for irrigation and/or infiltration; • Confirm that energy required for IAPS is less than 10kWh/PE/y; • Confirm the construction costs for a 2ML/d IAPS; • Integrate co-product streams for valorisation via community engagement; and • Technology transfer and operator training. Unfortunately, the partner DM found itself in the unenviable situation of having exhausted all funds it had committed to this and other infrastructure projects. Despite every effort on the part of the WRC and the project team, no further activity was possible and on 20 May 2016, a decision to terminate this project was taken and communicated to the DM as follows: “… has reviewed progress for project … and noted the risks relating to challenges regarding environmental impact assessment and regulatory licences approvals as well as failure by Chris Hani Local(sic) Municipality to secure co-funding for project implementation. Based on the outcomes of this review, the WRC would proceed and terminate project.” Again, both implementation of IAPS technology and realisation of its 18 downstream benefits (that is, clean water, renewable energy, and biomass) at commercial demonstrator scale had been foiled by circumstances beyond control and comprehension. Case study 2 An amount of R13.5-million was awarded by the DST to Umjindi (Mbombela) LM for implementation of an IAPS. Following a series of site visits as well as engagement and liaison with the Umjindi LM mayoral committee, a concept project proposal was accepted and underpinned by signature of a memorandum of agreement between the LM and a consortium that included EBRU and the appointed consulting engineers. The project proceeded without hindrance through the inception and preliminary design stages with an estimated cost to construct a 1ML/d IAPS of R12.5-million. Measurable deliverables were to include: • Increased municipal sewage treatment capacity by up to 5 000 PE; • Production of >250ML/y clean water for irrigation or infiltration; • Confirmation that energy needed for IAPS is <10kWh/y/PE; • Confirmation of construction costs for a 0.75ML/d IAPS; • Production of 5 000–7 500 kg/y algae-based fertiliser; and • Promotion of technology to municipalities for municipal wastewater treatment. By final design stage, nearly six months later, the cost estimate to build this 1ML/d IAPS had escalated to >R20-million. Clearly, intervention and redirection were required. After substantial effort on the part of EBRU to facilitate an iterative process that lasted approximately six months and was accompanied by the submission of a series of IAPS designs, a revised final design for a 0.75ML/d IAPS was accepted. This EBRU-approved design was used by the appointed consultants to secure environmental authorisation (EA), which was granted by the Department of Agriculture, Rural Development, Land & Environmental Affairs, Mpumalanga, on 29 August 2017. Even so, it was not long before this project was also to be derailed. First, and in the interim, an open public tender for construction of the 0.75ML/d IAPS was carried out. The tender window closed with just eight bids received as shown in Table 1. Also shown, is the cost estimate (in bold) for the IAPS determined by the consulting engineers. Water Sewage & Effluent March/April 2019 Table 1: Outcome of an open public tender for construction of the 0.75ML per day IAPS Name of tenderer Tendered amount (ZAR incl. VAT) CIDB grading A 23,336,716.00 7CEPE B 22,474,241.29 6CEPE C 20,489,676.57 6CEPE D 20,193,697.96 7CEPE E 19,266,021.09 7CEPE F 19,135,926.35 6CE G 17,042,456.78 7CEPE H 16,352,927.45 6CEPE Cost estimate 13,177,157.02 by CE >6CE It is clear that the outcome of this tender yielded bids that were for reasons unknown to the authors, R3-million to R10-million above the cost estimate and far in excess of the available funding. Second, based on the above estimates and in the absence of a proper tender evaluation report, it was irrationally argued by representatives of a reference/advisory group that the bespoke IAPS was ‘flawed’ and should be subject to redesign for re-costing. Indeed, in a report to the WRC and the EBRU-led project team it was stated: “Due to the simplicity of the design, the construction costs of IAPS plants should be far lower than the cost of activated sludge (AS) systems and other technologies of equivalent capacity. … the cost of a 1 megaliter(sic) activated sludge (AS) plant is expected to be in the region R12-million to R15- million. … the lowest tender was in the range of approximately R17-million for a 0.75 megaliter(sic) plant — extrapolating this means an order of magnitude of R23-million for a 1 megaliter(sic) IAPS plant. The design of the plant was also questioned. It was decided that the design should be re-visited by members.” It seems that the reference/advisory group had paid little attention to the detail of the approved IAPS design, which had been costed at ~R13.2-million. Nevertheless, the project team facilitated a redesign exercise, which was carried out by an independent registered professional engineer. EBRU determined that the resultant process and financials www.waterafrica.co.za