Water, Sewage & Effluent July August 2018 | Page 20

Retains cell at design thickness Even when care is taken, it is inevitable that the cells will be stood upon. The taut rigging bounces back and so restores the cell to the original design thickness. If the grout mix had been a bit heavy and depressed the cells, they slowly revert to their original levels and it may be necessary to top them up. The cells therefore act as a template to ensure that the flexible cast slab meets the design thickness. Working on the slopes The rebar pegs must extend through the bitumen layer so that the upper Hyson Cells layer can be rigged without needing to drive new pegs through the bitumen and so threaten its integrity. These pegs were used as supports for horizontal formers that allowed the workers to walk without having to stand on the empty cells. However, it is important that these pegs do not protrude above the final surface as they could puncture vehicle tyres. The workers wore safety harnesses. The dry Waterblok can be walked upon, so placing the final layer of Hyson Cells without use of the formers was not a problem with the help of the harnesses. In collaboration with Hyson Cells’ experience and guidance, Süllwald Bouers was rewarded by a significant improvement in production and lowered costs, resulting in a high-quality job. u Installation at Phalaborwa – speed of construction Self-levelling slump used on floor: A slump of 100mm was used for the grout for the dam’s floor. This was placed directly from the ready-mix truck. The discharge chutes were swung from side to side to help distribute the fill over as wide an area as possible. The mix had good flow characteristics because of the use of river sand, with no other aggregate, and was largely self-levelling. Installation speeds of 400m² per day were achieved on the floor of the dam. Liner constructed concurrent with earthworks: As soon as the bottom of the dam had been prepared, it was possible to commence constructing the waterproof liner on the floor concurrent with the earthworks construction of the sidewalls. The walls must be stable in their own right and in this case, Hyson Cells was not called upon to achieve stabilisation, although the soil nailing of the liner to the underlying material assisted in this regard. While the slopes are compacted to the engineer’s specification, Hyson Cells is more forgiving on small displacements that may nevertheless occur. List of professionals Client Phalaborwa Mining Company Project Relocation of Raw & Potable Water Reservoirs Consulting engineers Knight Piesold Main contractor L A Crushers Subcontractor Süllwald Bouers for Hyson Cells liner 18 Gravity-assisted flow of grout from head of slope: The ready-mix truck placed