Water, Sewage & Effluent July-August 2017 | Page 17

*Contributors: CESA, Corestruc, and QC4 Civils. thickness of 450mm. The structure features a 700mm diameter inlet pipe, two 800mm diameter outlet pipes, a 600mm diameter scour pipe, and 800mm diameter reservoir overflow pipe. From the outset, it was decided that the roof of the structure would be constructed with precast concrete elements to save time on the construction programme, in keeping with the urgency of water infrastructure being built. The project cut eight months off the construction programme, allowing the reservoir to be delivered in 11 months. The reservoir roof comprises more than 2 300m 2 of slabs, each up to 250mm thick. They are supported by 16 columns and 18 beams, weighing 12.3 tons and 7.5 tons, respectively. These were manufactured by Corestruc and stored before delivery to site, ahead of installation in February, which commenced when 80% of the walls had been cast. The construction of the reservoir wall alone was an impressive achievement, fast-tracked with a new climbing system designed and supplied by Form-Scaff, the civil engineering “Water is almost more important than nuclear at this stage.” Elsie Snyman, presenting the CESA report. Water Sewage & Effluent July/August 2017 Precast concrete elements being positioned. contractors. In as little as two weeks, 747m 2 per section could be erected, as opposed to the initial plan of 200m 2 per section. Construction of the wall and installation of the post-tensioning system followed the installation of the internal pipes, pouring of the reinforced concrete foundation, installation of load-bearing pads for the wall, and completion of the subsurface drainage system. This programme was divided into three sections and four lifts. The floor slab had also been cast, while the bases and plinths were ready to receive the columns. Equipped with a state-of-the-art theodolite, Corestruc’s team lifted and fastened the components into place, achieving tolerances of about 20mm at heights of 15 metres. A total of 2 000m 2 of precast items were installed in eight working days — a feat Corestruc’s Willie de Jager attributes to the extensive upfront planning. Once Corestruc had completed its operations, the civil engineering contractor’s team started installing water proofing and covering it with a stone layer. They installed the tendons and commenced tensioning, followed by grouting. A lightning protection system was installed, and the reservoir cleaned and inside surfaces chlorinated before filling the structure and undertaking waterproof testing. An added benefit of Corestruc’s technology is the high durability of the roof, with all the elements manufactured from a 55MPa concrete — far exceeding the 40MPa specification of the in situ material. This contributes to the overall performance of the asset, reducing maintenance requirements of the structure and costly rebuilds. u 15