The Ingenieur Vol. 65 Water Power | Page 74

INGENIEUR is actually very wide encompassing acts, defaults, breaches, omissions and even some breaches of statutory duty.68 ●● ●● notwithstanding, the apparently wide scope of the contractor’s said liability, it is nevertheless ameliorated by expressly stipulated exceptions; these being mainly in regard to: >> those ‘acts or defaults’69 caused by the employer and/or persons for whom the employer is responsible;70 >> the persons subject to this provision are the employer, the consultants, contract administrators or their authorised representative; and >> those losses or damages caused by specified perils where the employer has assumed the risk under any insurance policies taken up by the latter;71 >> these persons are absolved of liability by reason of ‘any negligence or omission’ on their part or ‘in failing to supervise or control the contractor’s site operations or methods of working or temporary works, or to detect or prevent or remedy defective work, or to ensure proper performance of any obligation of the contractor under the contract’.76 >> those arising upon the permanent use or occupation of the works or any part of the works by the employer;72 and >> those arising due to the unavoidable consequence of the contractor’s execution of the works or the making good of the defects of the works in accordance with the contract.73 D Chappell and V Powell-Smith in The JCT Design and Build Contract74 are of the opinion that the contractor’s liability does not also apply to loss or damage ‘ … to the works or materials on site up to the date of practical completion, partial possession of a particular part or determination’. 68 69 70 71 72 73 74 75 76 77 6 72 in regard to the first exception above, most conditions of contract now expressly state that notwithstanding the presence of the said exception, the contractor’s indemnities shall not be defeated nor reduced in the event the employer or its contract administrators or their authorised representatives have negligently caused or contributed to the loss or damage resulting thereby.75 Here, it should be noted that: Despite attempts by employers to shift the said liability to the contractor through such express stipulations, it is clear that the courts construe such provisions very strictly, often applying the ‘contra proferantum’ rule of construction. In Arthur White (Contractors) Ltd v Tarmac Civil Engineering Ltd,77 it was held that clear words must be used by the employer to allow it to enforce the indemnity clause notwithstanding the employer’s own liability for negligence to the third party. See Letang v Cooper [1965] 1 QB 232. This includes ‘negligence, omissions, etc.’. See cl 38.2(b) JKR Forms 203 & 203A (Rev 1/2010), etc. See cls 20B.1–B.5 or 20C.1–C.5 PAM Contract 2006 (With Quantities), PAM Contract 2006 (Without Quantities), etc. See cl 21.1(2)(a) IEM.CE 2011 and ME.2012 Forms. See cl 21.1(2)(b) IEM.CE 2011 and ME.2012 Forms. (2nd Edn) p 255. See cl 18.4 PAM Contract 2006 (With Quantities), PAM Contract 2006 (Without Quantities); cl 24.4 JKR Sarawak Form (2006), etc. Ibid; see also Sukumaran v Building Construction Co (Malaya) Ltd [1969] 1 MLJ 233. [1967] 3 All ER 586, [1967] 1 WLR 1508, HL; see also Walters v Whessoe Ltd and Shell Refining Co Ltd [1968] 2 All ER 816. VOL - MARCH 2016 VOL65 55JANUARY JUNE 2013