The Ingenieur Vol. 65 Water Power | Page 16

INGENIEUR MANAGING CHANGED CONDITIONS DURING CONSTRUCTION The original tender design was based on the premise that the ridge must be retained at least EL 46m so that the original reservoir storage can be retained. As the Penang State Government agreed to lower the existing reservoir to EL 34m the ridge was cut down to EL 35m. This allowed a balancing channel to be constructed to connect the left and right reservoir. This meant a single draw-off works was possible. The draw-off tower at the right valley could be omitted and replaced with a low level draw-off. Other works such as access bridge to the draw-off tower, extension of existing culvert to accommodate heightening of existing dam could be omitted. The modification to the design described above resulted in saving of over RM50 million from omission of permanent works and import of earthfill materials. Besides saving in cost and time, it also resolved the problem of shortage of construction materials, and mitigated the risk of construction and potential social and environmental problems. CHANGE OF DESIGN Revised Design of Dam Heightening The tender design for raising the height of the existing dam embankment from crest level EL45.72m to EL56.6 m was confined to downstream slope (see Figure 14). A new cut off system consisted of a clay core at the raised portion of the dam embankment, a concrete cutoff wall through the downstream slope of existing dam terminating at bed rock and a grout curtain below the concrete wall. With the omission of draw-off tower and access bridge at the upstream slope, it was feasible to raise the dam by filling on both upstream and downstream slopes of the existing dam. The clay core of the raised dam was inclined and integrated with the clay core of the existing dam (see Figure 15). The revised design educed the extent of settlement. The chimney filter and internal drainage system of the existing dam was retained. 6 14 VOL - MARCH 2016 VOL65 55JANUARY JUNE 2013 The revised design resulted in moving the toe of the raised dam further away from Sg. Lembu Road, mitigating the problem of interference with the public road during construction. Revised Layout of Spillway The layout plan of the tender design of the spillway was revised. The spillway chute was curved in order to avoid the filled embankment of raised dam. It was hydraulically not efficient and its construction more complicated. The revised dam raising design resulted in more space available at the right abutment for a straight spillway chute which was hydraulically more efficient (see Figure 16). CONTRACTUAL IMPLICATIONS RELATED TO DESIGN CHANGE The revision of design during the construction stage resulted in contractual claims by the contractor on the basis of changed conditions. However, the impact on the contract was far outweighed by the significant saving in construction costs and other benefits related to technical and environmental factors. The option of do nothing would forego the opportunity to add value to the project. Satisfactory execution of this major dam project required the consultant and implementing agency to be able to manage situations without causing delay and cost over-run. CONCLUDING REMARKS Completing such a major civil engineering project in a populated area was not an easy task. The successful completion of the Stage 1 dam expansion project in July 2015 demonstrates that through the co-operation and collective effort of the project developer, land owner, consultants and contractors, many challenges involving technical problems and contractual issues can be managed and brought to completion in relatively short period of four years. The spirit of partnership along with the willingness to deliver are the keys to responding to changing conditions which are inevitable in large dam projects and water supply infrastructure.