The Civil Engineering Contractor November 2018 | Page 30

INSIGHT One of the project’s challenges is working in a harsh mountainous environment. Phase II is expected to ensure a reliable water supply to South Africa by 2026 that will meet the demands of the Gauteng region, increasing the current supply rate of 780-million m 3 /year from the LHWP to the Vaal System by approximately 465-million m 3 to make a total of 1 270-million m 3 / year. Phase II is equally significant for Lesotho. The existing 72MW Muela hydropower station was built under Phase I of the project. Under Phase II, the hydropower generation capacity of the scheme will be increased. The 1 200MW Kobong Pumped Storage Scheme, or an alternative scheme as articulated in the bi-national Phase II agreement, is currently still in the feasibility phase. The current estimate is that the cost of Phase II at completion will be in the order of R25-billion for the South African water transfer component alone, with the Lesotho power generation component not yet quantified. South Africa will bear the costs related to the water transfer component, while Lesotho will bear 28 | CEC November 2018 the costs related to the hydropower component and its related social and environmental costs. “The hydropower scheme is still in the feasibility stage, along with proposals to use the water for ancillary developmental projects, whether irrigation or aquaculture, such as the trout export operation already established during Phase I at Katse Dam. From the feasibility stage it was envisaged that we would employ two tunnel boring machines (TBMs) drilling approximately 15km of tunnels from opposite ends to meet in the middle, with the western 8km leg envisaged to be a drill-and- blast. An interesting aspect of the project is that the western part of the tunnel end consists of an existing dam [Katse] already full of water, so we will have to have an interesting entry beneath the water. For the hydropower component, we’ve had to study the pump storage option and conventional options, and these are ongoing,” says Tente. The project authorities recently received a recommendation regarding the options for hydropower and decided to defer the power storage option and continue with the conventional option to a bankable feasibility. To date, he says, about 27 different contracts have already been signed for consultancy services since the bilateral agreement was signed in 2011, relating to engineering, environment, construction, and various hydropower services. Tente notes perceptions of conflicting interests between Lesotho citizens and South African citizens, given that Lesotho wants to maximise power generation and South Africa is keen to store water for greater water security. “We’re looking at the two schemes (water transfer and hydropower) being commissioned at the same time. We have an Advanced Infrastructure Programme: Because the project is going to be in the heart of the highland (where currently there is no modern infrastructure), we need to create appropriate infrastructure in terms of housing in the form of a construction www.civilsonline.co.za