The Civil Engineering Contractor May 2019 | Page 30

FEATURE: PILING AND LATERAL SUPPORT The range of drill sizes for different-diameter piles. (which is the only time the entire plant shuts down), as well as 24-hour work. We are piling in a vast area of rock, boulders, and concrete (from previous works) of what is atrocious conditions because nobody knows what’s under there. It’s an interesting job in which we are employing a self- drilling anchor technique (SDA). This involves installing a small hollow bar into a small hole which is percussion drilled and grouted. It is this mini- pile configuration that carries the load of the structure above.” Another option for piling is dynamic compaction, which was not used on this site, but which is also sometimes employed when ground conditions do not suit piling. Whittaker says this option would normally be used only on a large site. “It is not an exact art, and there can be complications if it is not done correctly. It is also time- consuming.” It has, for instance, been used on the CEOCO project, profiled in this month’s On Site feature (page 12). MegaPile company has also been involved in a prestigious project called Sandton Court in the heart of Rivonia, which was interesting from the viewpoint that it was surrounded by developed adjacent properties and therefore needed considerable piling and lateral support to protect the walls from caving in as the contractor excavated down. The company is also involved with developer Interprop 28 | CEC May 2019 on the piling and lateral support for the Oxford Parks Development, on Oxford Road, Rosebank, where there are five mixed-use precincts being established at the moment. “We’ve also recently completed a project called ‘Rockefeller’ on the foreshore in Cape Town, having only recently opened our branch in the Mother City.” Gauteng Piling has recently been involved in the Atria project in Waterfall: consisting of two office buildings, Atria East and Atria West, which when complete will comprise approximately 7 000m² each, with floor plates that will range between 1 300m² and 1 500m², a 180-bedroom hotel, and 120 residential apartments. Maas says their component of the project consists of about 240 piles. “It was interesting because the ground had areas of shallow rock and we had to drill into the very hard rock to get the uplift capacity required for two cores. We prefer to stick to our knitting of augered piles, although we also do various other types of piles.” Franki Africa is well represented on the continent, having recently completed projects in Mauritius, Angola, Ghana, Mozambique, Tanzania, Uganda, Swaziland, Botswana, and Zambia. One of Franki’s project achievements of late is the piling it undertook at the Multisports Complex, Mauritius. This involves the construction of a new sports complex for the Indian Ocean Games scheduled for July 2019 at Côte d’Or, St Pierre, Mauritius, and includes athletic training grounds and track, a football pitch, an aquatic centre, and a multipurpose gym on behalf of Mauritius Multisports Infrastructure Limited. In an article on Franki’s website, Mauritius country manager Yannis Mongelard says that the tender, which was launched in December 2017 with anticipated start in early 2018, stipulated 96 days for the piling work. “This was not possible for a host of different reasons at that time,” he says. “We submitted a solution which was cheaper, allowed for an earlier start and which could considerably cut down on the length of the job under normal circumstances. Moreover, it enabled us to work with the plant we had on the island at the time, which contributed significantly to the cost saving on the project.” Mongelard adds that from the original piling-only solution in the tender, Franki further enhanced efficiencies with a solution comprising a mix of piling and ground improvement. “The original tender specs involved the installation of more than 850 temporary cased auger piles of various sizes drilled to an average depth of 21m. Our ultimate solution comprised ground improvement in conjunction with a mix of piling techniques optimised to support each of the structures.” He explains that piling and ground improvement was required, following geotechnical investigations that found worse-than-expected ground conditions. “Moreover, the required bearing capacity of the backfilled soils could not be achieved, so deep foundations (piles) were opted for.” While these solutions could have cut down on production time, it turned out that high rainfall and the clayey platform made it almost impossible to achieve the daily minimum production from the start. In addition, the platform works could not proceed because the www.civilsonline.co.za