The Civil Engineering Contractor May 2019 | Page 24

ON SITE: PROJECT 2 Precast concrete slabs were manufactured by CoreSlab. de Bruin, MD of CoreSlab, explains that the company manufactured I-type beams for the project, with installation done by Corestruc once the bearings were installed. Corestruc is the installation arm of CoreSlab. “We supplied 210 precast-concrete beams for the bridge, and each span comprises 21 beams.” Delivery of the 210 beams was a logistical challenge, considering space constraints on site. Katzke explains that they were, therefore, supplied on a just-in-time basis rather than being offloaded all at one go, as the bearings on which they rest were consecutively completed. “They were consequently stored at CoreSlab’s factory and installed as the bearings were completed. “The beams consequently are conventionally transported straight from factory to site and lifted directly from the truck trailers using a mobile crane from CoreHire. There are five beams per load, each beam weighing 2.8t, enabling us to complete two spans a day. Once all the beams are laid, we will pour concrete on the central slab, which will facilitate access to the bridge at that level, 22 | CEC May 2019 enabling us to easily construct the barrier wall side section, drainage pipes, and service ducts. The side section can be done with the precast acting as shuttering. This is more efficient and will ensure the accuracy required for this component of the work,” says Katzke. He notes that the project demands the same high standards as South Africa. SABS standards are applied throughout and the FIDIC Red Book form of contract is being used on this project. “We are close to South Africa in this regard.” The bridge site has its own batching plant, with aggregate for the concrete sourced from a crusher in Selebi Phikwe, which recycles mine waste rock on site. This was more economic, as only tertiary crushing and screening was necessary, while also mitigating the need to open borrow pits. “Aggregate and sand were stockpiled here for batching on the Botswana side, as a contingency for flooding. The concrete batching plant has a capacity of between 200m 3 and 300m 3 a day for a 15MPa blinding material and 35MPa material for structural requirements. An independent laboratory was operated The old bridge alongside the new one being built. by the client to test the concrete. On every pour, we do a slump test, something which was possible considering the smaller pours.” Truck-mounted booms assist with pouring at that level, enabling one section to be completed each day in continuous pour. The relief culverts were to be done in situ, but the design opted for prefabricated units from Rocla on both sides. Project challenges Like any project, Platjan Bridge came with its challenges, says Katzke. The Limpopo’s watershed area extends as far as Johannesburg, which saw a huge amount of rain flooding into the Crocodile River and hence into the Limpopo. “We struggled at the start due to flooding during wet season — February 2018 saw a massive flood on the river. We had to use large pumps to remove water and isolate the pier bases at that time. Thereafter, we built a coffer dam that also served as a platform for the mobile crane, as the existing bridge was too small for the machine with its outriggers fully extended. Once the www.civilsonline.co.za