The Civil Engineering Contractor May 2019 | Page 18

ON SITE: PROJECT 1 Soya processing plant steel erection in the foreground with MySilo soya silos in the background. adjacent industrial sites were piled, but those structures are more substantial), though we eventually went with dynamic compaction below all the silos, the boilers, and the new soya processing plant. This wasn’t necessary for the roads.” Maitre explains this process: “We used large cranes to lift a 12.5t block of steel and repeatedly dropped it from a height of 22m. That gives you good foundation bearing for a depth in excess of 12m. We were looking for good bearing for 8m to 12m and they achieved it. This adds considerably to the costs — it took two rigs and was time-consuming. The result was that a lot of the silos arrived before we were ready and had to be stored in warehouses until we had the concrete bases in readiness. We have avoided this aspect with the boilers, despite the rains we have been having recently [February/ March].” An unexpected plant shutdown required maintenance of the solvent plant. This was scheduled at short notice and was under way at the time of the Civil Engineering Contractor visit. Maitre says this presented an ideal opportunity to commence work on the solvent plant and surrounds — but also required ADA to complete 16 | CEC May 2019 all its design work and client briefings within three weeks to facilitate work during the plant downtime. “This made it a project within a project, as we had to complete all this work within the four-week shutdown window,” he says. Concrete longevity roads for Of interest is that the developers have opted for an entirely concrete road. “Because the site will be extensively developed, the high traffic load of trucks will be using hydraulics and manoeuvring in tight spaces — putting extra wear on the road surface. Hence, we preferred heavy- duty concrete to asphalt or paving. The loss of any downtime due to road wear and tear would cost the production process far in excess of any additional upfront cost of road surfacing.” Coincidentally, says Maitre, concrete roads are one of his personal particular interests, having written his university thesis on the subject and he liaised with The Concrete Institute’s Bryan Perrie on it many years ago. “Ever since then, I’ve had a passion for concrete slabs on the ground. The failures are extensive and well documented. I interacted closely with Bryan on ultra-thin concrete layers they’ve been investigating of late, and after thorough discussion, we went for conventional un-reinforced concrete. We’re casting right now in the harshest of climatic and weather conditions: in the heat of summer and also during high rainfall, both of which can compromise concrete road construction. We concentrate on testing of the factors that can compromise concrete — making sure it has as low a water content as possible, the lowest slump as practically possible, but at the same time still practical from a workability point of view. We dictated that the ready-mix supplier takes a slump test of every single ready-mix concrete truck coming in, and any truck that was in excess of 100mm was sent away.” Ready-mix suppliers have standard mixes that have been tested, but conditions of rain and temperature can cause variances, causing variable slump results due to wet sand and stone in the mix. Too much moisture can cause shrinking and cracks in the concrete — “We want to avoid that upfront. Often people don’t fully realise that concrete on the ground has a very high risk of failure. “Innocuous as pouring concrete on the ground may seem, there’s a whole range of factors which influence the outcome: moisture on the ground, www.civilsonline.co.za