SSIP Annual Reports 2015 Annual Report | Page 32

32 In Review

PHASE 1 METRICS | As of December 2015
SSIP Projects by Phase
There are currently 66 SSIP Phase 1 Projects underway ranging from Pre-Planning to Completion .
10
Phase 1 Expenditures To-date expenditures and remaining authorized budget for SSIP Phase 1 .
Expended
$ 0.212B
8

66

24
Remaining
$ 2.5B
7
8
9
Phase 1 Completion Percentage of planned SSIP Phase 1 Projects complete .

7.8 % PHASE 1

PROJECTS
■ Pre-Planning
■ Planning
■ Design
■ Bid & Award
■ Construction
■ Completed
0 % 100 %
Local Business Enterprise Participation
The contract participation by Local Business Enterprise ( LBE ) subcontractors is based on total invoiced amount to date compared to the advertised LBE Sub participation Goal established by the Contracting Monitoring Division ( CMD ).
Local Hours
San Francisco residents have worked nearly 56K of the total 148K craft hours on SSIP projects . This equates to 37.8 % of the total hours , exceeding the Local Hire requirements of 20-30 % depending on the project .
25 %
■ Goal ■ Actual
20 %

37.8 %

Total Craft Hours Worked by San Francisco Residents
15 %
10 %
5 %
0 %
CS-315 ( Geo-Tech )
CS-169 ( CBSIP )
CS-235 ( BDFP )
CS-165 ( Program Management )
WW-541 ( O2 Plant )
Wages Earned by

$ 2.7 + MILLIONSan Francisco Residents

Annual Report 2015