SSIP Annual Reports 2015 Annual Report | Page 19

19 Renderings of EIPs Status of Projects Sunset Boulevard Greenway Construction began August 2015 and is expected through 2017. Holloway Green Street Construction is expected Winter 2016 and is expected through Summer 2017. Mission and Valencia Streets Green Gateway Construction is expected Winter 2016 through Fall 2016. Chinatown Green Alley Construction is expected Spring 2016 through Spring 2017. Visitacion Valley Green Nodes Construction is expected Spring 2016 through Spring 2017. Wiggle Neighborhood Green Corridor Construction is expected Fall 2016 through Summer 2017. Baker Beach Green Street Construction is expected Spring 2017 through Summer 2018. Upper Yosemite Creek Daylighting Construction is expected Spring 2018 through Winter 2018. SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.