seatec - Finnish marine technology review 1/2011 | Page 34

we’re expecting to float her out on 17 February,” Uusitalo says in early January. At the time, about half of the hull below the waterline has been painted. All and all, there are 600 people hard at work on the vessel. “All blocks are now OK’d for lifting and we’re looking to lift the last block – which is the chimney – during Week Four.” All through spring and early summer the construction should keep advancing rapidly, until the ferry is ready for its sea trials, scheduled for the first week of July. The date for delivery is already marked down in Uusitalo’s calendar: 1 September. Despite the hectic schedule, Uusitalo is confident that the shipyard will make the autumn deadline. Since France is the shipyard about three weeks in advance. VIVE LA FRANCE! second ship of a series, it is much easier This, in turn, required some creative ac- While Spirit of Britain is now gone, Uusi- to build – everybody already ۛ