Plumbing Africa March 2018 | Page 39

PROJECT 37 Rosebank Fire Station gets a facelift Rosebank Fire Station has a rich heritage and a long history dating back to the 1930s. The original building is one of the oldest and most well known in the area. By Dineo Phoshoko Whilst having a captivating modern design, the new building is still respectful to the heritage of the protected fire station. GDM Plumbing & Projects was responsible for all plumbing-related work required for the new building. GDM began work on the project in November 2016, with completion expected at the beginning of March 2018. On the terraces, a cast-in-concrete Hydrotec floor drain system was installed. More than 150 drains reticulate down the side of the building in the aluminium glass facade and are collected into a main HDPE launder pipe in the basement levels, flowing down four basement level floors and ultimately discharging into the municipality stormwater system. SYSTEM IN DETAIL Water supply The plumbing company installed a domestic water supply system, which is fed from the municipal water supply down to the fourth basement level. In the basement, the water is stored in two 5 000ℓ Jojo tanks. The water from the system is used to supply the building’s various sanitary fittings. Another area of the building that required a stormwater system is the car park. For this, two sump pumps were installed in catch pits in the building. This catches any subsurface and car park run-off and pumps it from the building into the municipality stormwater system. The water is then pumped up the 16 storeys of the building through a Grundfos Hydro MPC-E 3 booster pump in a main water line (80mm galvanised pipe). GDM used pressure-reducing valves (PRVs) to create distinctive pressure zones on the various floors of the building, whilst maintaining the higher pressure in the main line to reach the upper levels of the building. The water splits off the main galvanised line and is fed via the Geberit Mepla pipe system to numerous ablution blocks and kitchenettes. Sewer For the sewer waste system, Geberit’s HDPE pipes were installed to collect all sewer waste and feed it to the external municipal sewer line. Stormwater drainage GDM also worked on the stormwater drainage system for the building. For roof drainage, the Geberit Pluvia syphonic rainwater collection system was incorporated on the roof of the building. This is made up of 12 outlets on two floors that collect all water and reticulate it down to the ground floor and into the municipality stormwater system. www.plumbingafrica.co.za Power supply and backup The Grundfos booster pump uses an electrical feed to pump water from the basement to the entire building. To cater for power disruptions, the design team has made provision for the pump system to use power from the backup generator system. In the event of a municipal water cut, the two JoJo tanks store enough water to supply the building for eight hours during the water cut. CHALLENGES DURING THE PROJECT Working on a project of this magnitude, one is bound to experience numerous challenges. The biggest challenge for this project was installing the over 150 cast-in-floor drains to accommodate stormwater from the terrace areas. These needed to be perfectly aligned and spaced in confined areas. The main contractor, Aveng Grinaker- LTA, came up with a temporary steel channel system that was placed onto formwork decks prior to pouring concrete. The drains were then fixed directly to the system and the temporary steel system later removed. Another challenge was dealing with 10 different sewer stacks that ran directly through tenant office space. This would have been an enormous