Palm Beach Undergrounding Master Plan COMPLETE MP Online-v4 | Page 91

Executive Summary 8.0 Risk Assessment There are always risks involved with any project, and a project of this magnitude is no exception. These risks can be broadly described as risks that could impact the project schedule and/ or the project budget. By identifying these risks ahead of time, steps can be taken to mitigate them. Risks to Schedule Design / Pre-Construction Phase The Town of Palm Beach will be dependent on FPL, Comcast and AT&T to produce detailed design documents for their respective electrical and communications networks. From these plans, the Town’s design team led by Kimley-Horn prepares the bid documents used by the Town to procure the contractor to construct the work. The risks inherent with work being produced by entities not directly contracted under the Town is the Town’s limited control over the activities of those entities. For example, in the event of a significant weather impact, resources from each of the affected utilities may be reallocated to assist with the recovery efforts. Utility owners prioritize the provision of service to existing customers over design work. In such an event, the design work could be TOWN-WIDE UNDERGROUNDING OF UTILITIES PROGRAM MASTER PLAN DOCUMENT delayed under recovery efforts are complete. Therefore, this would have a negative schedule impact. The Town will need to secure the required equipment easements prior to construction. Over the life of this project, hundreds of easements will be required from property owners in the community. The negotiation process to procure these easements can take time, especially with absent or unwilling property owners. As a last resort, the eminent domain process can be employed but this too can be time consuming and could lead to delays in beginning the construction. Risks to schedule are also present during the bid phase. If the plans are unclear, or assign too much risk to a bidding contractor, undesirable consequences may result. Bid prices may be submitted that are higher than expected to account for the ambiguities or perceived risk, or qualified contractors may choose not to bid on the project. The latter is especially true in a robust economy where there is plenty of work in the local market. The re-bidding a project in an effort to receive more competitive bids would have an undesirable schedule impact. Construction Phase The project schedule could be delayed during the construction phase due to a number of factors including, but not limited to the following: y y Contractor’s ability to complete the work in the desired time frame due to staffing, equipment or sub-contractor issues y y Difficulty in coordinating the various utility owners to perform those work elements that cannot be performed by the Town’s contractor in a timely manner. For example, AT&T will not allow any forces other than their own to install their cabling and equipment. y y Unforeseen sub-surface conditions can result in project delays while alternate designs are performed to deal with the unforeseen condition y y Difficulty in coordinating the overhead to underground service conversion with absent or unwilling property owners. Communication service swaps can sometimes require attic access and must be performed by the utility company. Absentee or unwilling owners can make this access very difficult to obtain. y y Property owners whose service entrance equipment does not meet the National Electric Code (NEC) will need to have these service entrances replaced prior to conversion y y Difficulty in coordinating the various utility owners to perform the aerial cabling and utility pole removal. This work must be performed by the utility owners and cannot be started until all services are converted to the underground system. y y Adverse weather events during construction, such as tropical depressions or storms, hurricanes or extended periods of rain. Utility owners prioritize the provision and restoration of service to existing customers and will abandon a conversion project until recovery efforts are complete. Risks to Budget Design / Pre-Construction Phase The risk of cost overruns in the design phase is relatively small. Cost overruns in the design phase could result from the Town adding scope to the project.