Palm Beach Undergrounding Master Plan COMPLETE MP Online-v4 | Page 204
Town of Palm Beach
Master Planning Engineer’s Conceptual Opinion of
Probable Cost for Undergrounding
Phase 7 North
Item No.
Description
Amount
$1,020,000.00
1 FPL Overhead to Underground Conversion 2 AT&T Overhead to Underground Conversion $360,000.00
3 Comcast Overhead to Underground Conversion $250,000.00
4 Roadway and Private Property Restoration $910,000.00
5 FPL Direct Costs 6 AT&T Direct Costs $250,000.00
7 Comcast Direct Costs $110,000.00
8 FPL Service Conduit (Private Property) $270,000.00
9 Engineering/Permitting/Surveying $360,000.00
10 Construction Administration $260,000.00
11 Legal Fees
Credits
FPL Credit – 25% GAF Waiver $110,000.00
12
178 | CHAPTER TWELVE
$1,070,000.00
($570,000.00)
Subtotal Estimate – Today’s Dollars $4,400,000.00
Subtotal Estimate – Considering Inflation $5,250,000.00
Contingency $480,000.00
Total = $5,730,000
TOWN OF PALM BEACH