Palm Beach Undergrounding Master Plan COMPLETE MP Online-v4 | Page 202
Town of Palm Beach
Master Planning Engineer’s Conceptual Opinion of
Probable Cost for Undergrounding
Phase 6 North
Item No.
Description
Amount
1 FPL Overhead to Underground Conversion $980,000.00
2 AT&T Overhead to Underground Conversion $340,000.00
3 Comcast Overhead to Underground Conversion $240,000.00
4 Roadway and Private Property Restoration $880,000.00
5 FPL Direct Costs 6 AT&T Direct Costs $250,000.00
7 Comcast Direct Costs $110,000.00
8 FPL Service Conduit (Private Property) $260,000.00
9 Engineering/Permitting/Surveying $350,000.00
10 Construction Administration $260,000.00
11 Legal Fees
Credits
FPL Credit – 25% GAF Waiver $100,000.00
12
176 | CHAPTER TWELVE
$1,040,000.00
($550,000.00)
Subtotal Estimate – Today’s Dollars $4,260,000.00
Subtotal Estimate – Considering Inflation $4,940,000.00
Contingency $450,000.00
Total = $5,390,000