Palm Beach Undergrounding Master Plan COMPLETE MP Online-v4 | Page 202

Town of Palm Beach Master Planning Engineer’s Conceptual Opinion of Probable Cost for Undergrounding Phase 6 North Item No. Description Amount 1 FPL Overhead to Underground Conversion $980,000.00 2 AT&T Overhead to Underground Conversion $340,000.00 3 Comcast Overhead to Underground Conversion $240,000.00 4 Roadway and Private Property Restoration $880,000.00 5 FPL Direct Costs 6 AT&T Direct Costs $250,000.00 7 Comcast Direct Costs $110,000.00 8 FPL Service Conduit (Private Property) $260,000.00 9 Engineering/Permitting/Surveying $350,000.00 10 Construction Administration $260,000.00 11 Legal Fees Credits FPL Credit – 25% GAF Waiver $100,000.00 12 176 | CHAPTER TWELVE $1,040,000.00 ($550,000.00) Subtotal Estimate – Today’s Dollars $4,260,000.00 Subtotal Estimate – Considering Inflation $4,940,000.00 Contingency $450,000.00 Total = $5,390,000 TOWN OF PALM BEACH