Palm Beach Undergrounding Master Plan COMPLETE MP Online-v4 | Page 200

Town of Palm Beach Master Planning Engineer’s Conceptual Opinion of Probable Cost for Undergrounding Phase 5 North Item No. Description Amount $1,250,000.00 1 FPL Overhead to Underground Conversion 2 AT&T Overhead to Underground Conversion $430,000.00 3 Comcast Overhead to Underground Conversion $300,000.00 4 Roadway and Private Property Restoration $1,130,000.00 5 FPL Direct Costs $1,320,000.00 6 AT&T Direct Costs $310,000.00 7 Comcast Direct Costs $140,000.00 8 FPL Service Conduit (Private Property) $340,000.00 9 Engineering/Permitting/Surveying $440,000.00 10 Construction Administration $290,000.00 11 Legal Fees Credits FPL Credit – 25% GAF Waiver $130,000.00 12 174 | CHAPTER TWELVE ($700,000.00) Subtotal Estimate – Today’s Dollars $5,370,000.00 Subtotal Estimate – Considering Inflation $6,040,000.00 Contingency $550,000.00 Total = $6,590,000 TOWN OF PALM BEACH