Palm Beach Undergrounding Master Plan COMPLETE MP Online-v4 | Page 182

Line Item Category developed. The total costs for each sample project area were then divided by the length of overhead pole-line feet converted within the sample project area to develop a representative unit cost per pole-line foot converted that could be applied on a Town-wide basis to each of the program’s phase areas. The unit prices per pole-line foot of conversion were categorized into the appropriate line item category for use in the overall opinion of probable cost. A summary of each line item category outlined in the opinion of probable cost is in the table on the right. 12.4 Quantity Estimation To develop reasonably accurate quantity estimates for each phase of construction, GIS shape files developed during this Master Plan for roadways, parcels, existing overhead utility locations, and outside infrastructure project information (gas, water main, ACIP projects, paving projects, etc.) were imported into AutoCAD drafting software. Additional AutoCAD line work was developed by Kimley-Horn to estimate the approximate locations/ lengths of joint trench and roadway impacts within each phase. Aerial photography imported into AutoCAD in real-world coordinates was used to confirm the accuracy of the GIS data, as well as provide estimated roadway widths 156 | CHAPTER TWELVE Unit Costs Included in the Line Item Category FPL Overhead to Underground Conversion General Conditions related to electrical infrastructure installation (Mobilization, demobilization, Maintenance of Traffic, Bonds and Insurance, Pre- construction documentation, survey layout and record drawings), construction management fees, and installation of FPL provided conduit, cabling, and equipment in Town right-of-way and easements AT&T Overhead to Underground Conversion General Conditions related to AT&T conduit and pull box installation (Mobilization, demobilization, Maintenance of Traffic, Bonds and Insurance, Pre- construction documentation, survey layout and record drawings), construction management fees, and installation of conduit, vaults, and pull boxes in Town right-of-way and easements Comcast Overhead to Underground Conversion General Conditions related to Comcast installation (Mobilization, demobilization, Maintenance of Traffic, Bonds and Insurance, Pre-construction documentation, survey layout and record drawings), construction management fees, and installation of conduit in Town right-of-way and easements Roadway and Private Property Restoration Asphalt trench repair, sodding/grassing, bore pit repair, driveway restoration, equipment screening/landscaping, curb repair for conduit installation, right-of- way and private property restoration, construction management fees, and restoration after utility pole removal demolition FPL Direct Cost Provision of all electrical infrastructure materials, “Make-ready” costs for transition to underground system, overhead infrastructure removal and demolition At&T Direct Costs Provision and installation of all AT&T equipment and cabling within Town installed conduits, service conversions, and removal of overhead AT&T infrastructure Comcast Direct Cost Provision and installation of all Comcast vaults, equipment and cabling within Town installed conduits, service conversions, and removal of overhead Comcast infrastructure FPL Service Conduit Installation of FPL provided service conduit on private property At&T/Comcast Service Conduit Installation of At&T/Comcast service conduit on private property Engineering/Permitting/Surveying Estimated fees for engineering design and survey, easement sketch and legal descriptions, and permitting fees Construction Administration Estimated fees for construction engineering observation and Town support during construction Legal Fees Legal fees for easement acquisitions and other program legal support Pavement Milling and Resurfacing Costs related to milling and resurfacing of impacted roadways after completion of the undergrounding process FPL Credit – GAF Waiver Credit offered to municipalities who underground their facilities. This program qualifies for the maximum credit of 25% Pavement Milling and Resurfacing Cost Sharing There are costs related to pavement milling and resurfacing that can reasonably be shared by other programs including Town infrastructure projects (ACIP and CIP), watermain replacement, and gas main replacement TOWN OF PALM BEACH