Notification, Coordination, and Approval of Closures y y Contractors must notify the Town Engineer and FDOT (as applicable) at least six weeks in advance of any proposed closures. y y Contractor is advised that lane closures of any north-south thoroughfare will require Town Council Approval. y y A Town of Palm Beach Communication representative and a FDOT Communication representative (as applicable) shall coordinate all closure activity. y y Any work requiring a closure will need to have an approved traffic control plan and corresponding MOT permit from the Town of Palm Beach Public Works Department and FDOT (as applicable). y y All approved closures must be communicated to the Town on a weekly basis by the contractor during the week prior to the closure so the Town can include the closure in their weekly Traffic Report to the community. y y Final notification of weekend activities must be submitted by 5:00 p.m. Tuesday to the Town’s Communications (and FDOT Communications and the FDOT Traffic Operation Center (TOC) as required). y y The Town will produce a weekly media alert for all weekend traffic impacts as well as traffic impacts for the 88 | CHAPTER NINE upcoming week. A phone number should be published in these media alerts that allows impacted motorists to call and report observed issues with the MOT operations. y y Material hauls on local streets will be subject to the Town of Palm Beach, FDOT, City of West Palm Beach, and City of Lake Worth requirements and local ordinances. y y The Town’s Public Works Department will coordinate closures among projects through the MOT permitting process and keep the community apprised of upcoming closure activities through media releases. y y After approval of traffic control plans and associated closures and detours, communications shall be made to provide stakeholders a two-week advance notification of impending approved closures. y y Field personnel need to notify the Town Engineer, Design Engineer, FDOT Communications and FDOT TOC (as applicable) of any cancellations or changes in closure schedules. y y Contractor shall place advance closure notice information signs per Town of Palm Beach, City of Lake Worth, and FDOT requirements (as applicable) and advise affected businesses and residents at least two weeks in advance of impending approved closures. y y All roadway closures, material haul routes and detours shall be jointly approved by the Town of Palm Beach and the FDOT (as applicable), prior to implementation. Roadway closures, material haul routes, and detours through the City of West Palm Beach and the City of Lake Worth shall have appropriate agency approvals. y y Contractor shall submit the details of the contemplated activities and related traffic effects to the Engineer, City of West Palm Beach, and City of Lake Worth as needed to receive approval at least 21 days in advance of the contemplated activities that ma y impact those jurisdictions. y y In all cases where there are roadway impacts, the contractor shall assure that access is maintained or otherwise provided to and from abutting properties. After approval, contractor shall advise residents and businesses of any impending access restrictions. Full closure of roads in a manner that prevents access to residences and businesses will not be permitted. y y Temporary traffic control devices shall not be set up in advance of a closure unless approved by the Town and FDOT (as applicable). Upon completion of the closure, traffic control devices shall be entirely removed from the roadways and shoulders by the end of the work day. The devices may not be left or stockpiled on shoulders or in clear zone areas. y y The contractor shall provide schedules of daily activities and corresponding traffic control plans. This information shall be provided in advance and during construction progress meetings. The information provided shall specify the limits of the work activities and related traffic control plan by location, direction and time. The construction schedule and associated traffic control plans shall be developed in a format suitable for release to other agencies and the public, and shall be updated as necessary. Holidays y y Temporary lane closures are not allowed on holidays or weekends that adjoin a holiday. y y Contractors will remove all traffic control for temporary lane closures prior to holidays or weekends that adjoin a holiday. y y In most calendar years there will be 10 weekends in which closure activity is not allowed due to the holiday schedule. y y Lane closures that require an extended duration and are implemented with appropriate barriers, traffic control devices, and signage shall be allowed to remain in place during a holiday or holiday weekend. TOWN OF PALM BEACH