These are color coded and separated in the maps beginning on page 91 . The intent is to have available detour options as work occurs on the main roads ( thoroughfares ) and there is the necessity to detour traffic through the local roads . The local roads should always maintain access to local traffic and access to driveways .
The exhibits provide suggested cross streets for transportation management based on field visits conducted in August and October 2016 to verify lane widths were adequate to accommodate the detoured traffic . It should be noted that no singular cross street is recommended for a detour and where possible multiple adjacent roadways are recommended . By providing multiple options for the detour , the impact to the residential cross streets can be minimized . To promote drivers to use the earlier detour options and avoid the majority of drivers waiting until the last cross street before the road closure to detour , it is recommended that variable message signage be provided such that specific road names can be recommended for the detour .
The specific timing and implementation of closures and lane restrictions will be detailed in the maintenance of traffic plan to be submitted by the contractor . Specific conditions and recommendations contained in this traffic management plan will be communicated to the contractor in the construction
documents . The contractor shall always maintain access to local traffic and access to driveways .
Guidelines for others that occupy the roads :
• yLandscapers and other contractors should be restricted to parking on roads that do not have lane closures , or are outside the affected work area , unless otherwise approved by the Engineer or Town
• yOther contractors should be restricted to working on roads that do not have on-going undergrounding work , unless otherwise approved by the Engineer or Town
• yAccess to cyclists and pedestrians will be described in the construction documents for implementation by the contractor
9.6 Traffic-Related Work Restrictions :
The contractor shall maintain the same number of travel lanes and parking lanes as existing in each direction open to traffic at all times , except as noted herein .
Full Closures or Partial Closures
y • Full or partial closures will be allowed Sunday night through Friday morning from 10:00 p . m . to 5 a . m .
• yFull or partial closures will be allowed Friday night from 10:00 p . m . to Saturday 7:00 a . m .
• yFull or partial closures will be allowed Saturday night 10:00 p . m . to Sunday 7:00 a . m .
• yA full closure of the main northbound and southbound thoroughfares will not be allowed at the same time .
• yA full closure of any travel lane ( s ) that does not allow the maintenance of two-way travel at all times will require the use of flag men during the closure period .
• yA full closure of any travel lane ( s ) that will create a one-way travel direction , or complete roadway closure , will require advance approval from the Public Works Department
Night Time or Night Closures Shall Relate to the Following Time Periods :
• ySunday 10:00 p . m . to Monday 5:00 a . m . ( 7 hours )
• yMonday 10:00 p . m . to Tuesday 5:00 a . m . ( 7 hours )
• yTuesday 10:00 p . m . to Wednesday 5:00 a . m . ( 7 hours )
• yWednesday 10:00 p . m . to Thursday 5:00 a . m . ( 7 hours )
• yThursday 10:00 p . m . to Friday 5:00 a . m . ( 7 hours )
• yFriday 10:00 p . m . to Saturday 7:00 a . m . ( 9 hours )
• ySaturday 10:00 p . m . to Sunday 7:00 a . m . ( 9 hours )
Weekend Closures
• yWeekend closures will only be allowed when identified in the plans or special provisions
• yWeekend closures will be allowed from Friday at 10:00 p . m . to the subsequent Monday at 5:00 a . m .
Weekdays
• yMondays , Tuesdays , Wednesdays , Thursdays and Fridays that are not Town holidays shall be considered weekdays . The day after Thanksgiving shall be considered a holiday . A “ holiday weekend ” shall be defined as the period between noon on the weekday before a holiday and noon on the weekday after a holiday .
• yWork will not be allowed on Town observed holidays .
Conflicting Closures
• yNo two adjoining corridors may be closed in the same direction at the same time
• yNo two corridors that would act as alternates to each other may be closed at the same time