Palm Beach Undergrounding Master Plan COMPLETE MP Online-v4 | Page 105

Table 4 Anticipated Construction Sequence

Table 4 Anticipated Construction Sequence

Year Project Area Land Use Major Work Elements
2017 Phase 1 North Single Family Residential Undergrounding , Street Lighting , Watermain , Drainage 2017 Phase 1 South Multi-Family Residential Undergrounding , Drainage , Street Lighting 2017 Elsewhere in the Town
Australian Avenue sanitary sewer , Lake Trail Improvements , Ocean Outfall abandonment , Pump Station Improvements , FPU Gas Main Replacement , Southern Boulevard Bridge Replacement
2018 Phase 2 North Single Family Residential Undergrounding , Street Lighting , Watermain 2018 Phase 2 South Single Family Residential Undergrounding , Street Lighting , Watermain , FPU Gas Main Replacement , Southern Boulevard Bridge Replacement
2018 Elsewhere in the Town 2019 Phase 3 North Single Family Residential Undergrounding , Street Lighting , Watermain
Demolition and removal of overhead utilities from Phase 1 , Mast Arm Replacement / Upgrade , Pump Station Improvements , FPU Gas Main Replacement , Bradley Place Improvements
2019 Phase 3 South Single Family Residential Undergrounding , Street Lighting , Watermain , Pumps Station Improvements 2019 Elsewhere in the Town
Demolition and removal of overhead utilities from Phase 2 , Pump Station Improvements , FPU Gas Main Replacement , Southern Boulevard Bridge Replacement , Mast Arm Replacement / Upgrade
2020 Phase 4 North Single Family Residential Undergrounding , Street Lighting , Watermain
2020 Phase 4 South
2020 Elsewhere in the Town
Mixed-Use Commercial / Residential
Undergrounding , Street Lighting , Watermain , Pump Station Improvements
Demolition and removal of overhead utilities from Phase 3 , Pump Station Improvements , FPU Gas Main Replacement , Southern Boulevard Bridge Replacement
2021 Phase 5 North Single Family Residential Undergrounding , Street Lighting , Watermain
2021 Phase 5 South
2021 Elsewhere in the Town
Mixed-Use Commercial / Residential
Undergrounding , Street Lighting , Watermain , Signal Interconnect , FPU Gas Main Replacement
Demolition and removal of overhead utilities from Phase 4 , Pump Station Improvements , Southern Boulevard Street Lighting , FPU Gas Main Replacement , Southern Boulevard Bridge Replacement
2022 Phase 6 North Single Family Residential Undergrounding , Street Lighting , Watermain
2022 Phase 6 South
Mixed-Use Commercial / Residential
Undergrounding , Street Lighting , Watermain , Signal Interconnect
2022 Elsewhere in the Town Demolition and removal of overhead utilities from Phase 5 2023 Phase 7 North Single Family Residential Undergrounding , Street Lighting , Watermain
2023 Phase 7 South
Single Family / Multi-Family
Undergrounding , Street Lighting , Watermain
2023 Elsewhere in the Town Demolition and removal of overhead utilities from Phase 6
2024 Phase 8
Mixed-Use Commercial / Residential
Undergrounding , Watermain , Demolition and removal of overhead utilities 2024 Elsewhere in the Town Demolition and removal of overhead utilities from Phase 7
TOWN-WIDE UNDERGROUNDING OF UTILITIES PROGRAM MASTER PLAN DOCUMENT
TRANSPORTATION MANAGEMENT PLAN | 85