Construction—EMEA—Portugal—Commercial Buildings
Photos reprinted courtesy of Constructora SANJOSE, S.A. Representação em Portugal, Portugal
Afterwards, the General Contractor asked
DSI Construction Portugal to supply
DYWIDAG Bar Tendons and couplers that
were needed for tightening the concrete
blocks and holding them in place.
In total, DSI supplied 192 12 m long, 26.5mm
Ø DYWIDAG Bar Tendons. Furthermore, 384
26.5mm Ø couplers were used for a force-fit
connection of the post-tensioning bars.
This allowed further excavation and
terrain containment in order to reach the
necessary excavation pit depth of 12m.
By cooperating closely with the General
Contractor, DSI Portugal was able to supply
all necessary products and systems to
the jobsite on time. DSI is proud to have
contributed to a rehabilitation project
in one of Europe’s oldest cities.
Operator
Hotusa Hotels S.A., Spain
Owner
IMOCAIS - Fundo Especial de
Investimento Imobiliário Fechado,
Portugal
General Contractor
Constructora SANJOSE, S.A.
Representação em Portugal,
Portugal
Subcontractor
Constructora SANJOSE, S.A.
Representação em Portugal,
Portugal
Engineering
Engitarget - Gestão, Projecto e
Fiscalização de Empreendimentos, Lda,
Portugal
DSI Unit
DYWIDAG Sistemas Constructivos S.A.,
Portugal
DSC Scope
Production, supply
DYWIDAG Products
192 12 m long, 26.5mm Ø DYWIDAG Bar Post-
Tensioning Tendons, 384 26.5mm Ø couplers
117