Manoeuvring the 2nd Half into Position
Once it has been established that the first half is level, the 2nd half of the unit
can be prepared, the transport sheeting should be removed and an internal
inspection carried out prior to commencing further work, again, timber support
frames must remain in place until both halves are fully connected.
The aim is to get the 2nd half of the unit positioned as close as possible, and
parallel to the 1st. The ideal position is to have a consistent gap of about
50mm to 75mm, along the entire length and height of the unit.
Jack, Block and Level the 2nd Half of the Unit
The jacking and blocking of the 2nd half of the unit is essentially a repeat of the
process carried out for the 1st half.
The 2nd half of the unit needs to be lifted off th ??????????????????????)?????????????????????????????????????????????()A???????????????????????????????????()Q?????????????????????????????????)????????????????????????????????????(?????????????????)Q???????????????????????????)???????????????????????????)????????????????????????????????)?????????????????????????????????)????????????()I???????)??????()A??????????()??)??)?????((