Key Biscayne Master Plan 043944000.18w_Key_Biscayne_MP(forJooMag) | Page 9

1.0 EXECUTIVE SUMMARY situations include communicating information related to specific design and construction activities that specifically affect the individual resident or business owner. The following methods should be employed to communicate with individuals during the design and construction phases:    Direct email, telephone, and/or direct mailings Neighborhood meetings Individual meetings with residents/business owners As a lesson learned on prior projects it is recommended that direct mailings be made to inform residents and business owners that the contractor will be placing equipment within the right-of-way adjacent to their properties. This enables the project team to get ahead of and coordinate with property owners who may have questions or concerns regarding the equipment that will be located adjacent to their homes. This minimizes the impact to the community as they will know exactly what to expect regardless of whether or not they granted an easement. Consistent messaging should occur throughout the duration of the program to keep the community informed about the various stages of the process, the progress that is being made, and the goals and milestones that are being achieved. To that end, a brand logo and tag line has been developed so that residents can immediately identify communications related to this project. Opinion of Schedule Based on the Phasing and Sequencing Plan, an opinion of schedule was developed to better understand how each individual phase of the program would interact with each other during the implementation process. Schedule considerations were developed through discussions with the Village, area contractors with expertise in undergrounding, our experience with recent undergrounding projects, and the utility owners. Construction activity durations are based on reasonable production rates from area contractors with undergrounding expertise. Combining these production rates with mass quantities for the project that were developed as a part of the opinion of cost development yielded significant activity durations that were then incorporated into the overall schedule. Utility design timeframes experienced on other projects currently underway were also considered. Appropriate schedule contingencies were also applied to account for normal weather impacts, potential geological challenges (rock), and unforeseen conditions. The program schedule began in February 2018 with the development of this master plan. Subsequent to design of Phase 1, construction activities are expected to begin in the summer of 2020. Construction durations for each phase range from 18 to 24 months depending on the quantity of work to be performed and complexity of each Phase. To accelerate the work, the construction schedule for each phase overlaps the previous adjacent phase construction schedule by six months to one year. The overlap of the construction activities in each phase is subject to conduit installation being complete in the previous phase prior to allowing conduit installation activities to begin in the subsequent phase. This is done primarily to mitigate traffic impacts. There is an opportunity to compress the schedule further by splitting each phase up into two work areas, however, any further compression will be contingent on the utility company design schedules and easement acquisition timeframes. The final six months of the construction activity schedule for each phase is reserved for overhead infrastructure demolition. It is not expected that this will be a continuous construction activity. Experience with similar projects has shown that the coordination required with FPL, AT&T, and Comcast can be time consuming and they need to work sequentially rather than concurrently to remove facilities. Therefore, this activity requires a certain duration of time to be accomplished. Based on our opinion of schedule, all areas of the Village are anticipated to be converted underground by the end of 2025. Final pole removal is anticipated to be completed by the end of the first quarter in 2026. The schedule does contain time contingencies for normal weather impacts, rock conditions, and typical unforeseen conditions. It does not account for significant schedule impacts related to significant weather events that cause the utility owners to focus efforts on storm recovery rather than undergrounding. It also does not consider significant contractor issues related to litigation, bankruptcy, non-performance, and the like because these types of issues are impossible to predict. 5