Key Biscayne Master Plan 043944000.18w_Key_Biscayne_MP(forJooMag) | Page 83

8.0 RISK ASSESSMENT Schedule Risk Mitigation Design and Preconstruction Phase As utility owners do not have the same contractual obligations to the Village as the design team, it is particularly important to develop methods to mitigate the risk they present to the overall project schedule. To mitigate this risk, it is recommended the Village initiate design of multiple, separate work areas at one time and overlap phase schedules so the impact of a delay in the design of a single phase on the overall project schedule is reduced. By having multiple phases with multiple work areas per phase, the portion of the Village in active construction at any given time is small relative to the project size, therefore reducing the perceived impact to the community at any given time while providing schedule control benefits to the Village. By overlapping the phases, the utilities can design future phases while construction work is active in a previous phase. This provides additional time not only to complete the design work, but to identify and procure equipment easements. This reduces the risk to the overall project schedule if the design of any single phase is delayed due to storm recovery efforts. Certain significant pieces of equipment required for completion of the project have limited flexibility where they can be located in the final design of the underground system. An example would be a switch cabinet that marks the limit of a service area boundary defined by electrical load demand. Since these pieces of equipment must be located in certain areas, a longer duration to acquire the easement may be necessary if property owner negotiations or an eminent domain process are needed. Identifying these locations early in the planning and design process provides extended periods of time to acquire required easements prior to each project area going into construction. potential bidders and allows for lump sum bidding for various scopes of work. Lump sum bidding can be employed on infrastructure projects when the scope of work is clearly defined and the risk of quantity overruns is low. Unit price bidding is traditionally used on projects where quantities are likely to change because precise estimates cannot be made. Construction Phase To mitigate the risk the chosen contractor fails to perform the work within the desired schedule, we recommend:  requiring bidders submit historical evidence with their bid proposal to demonstrate past success in meeting schedules on similar projects  requiring bidders submit references with their bid proposal the Village can contact to discuss schedule performance on past similar projects  engaging a Construction Manager who has the authority to remove and replace poor performing subcontractors and/or to bring in additional resources when threats to the project schedule are identified. To mitigate the risk of unforeseen subsurface conditions impacting construction and to properly plan for the installation of the electric and communications infrastructure, we recommend record drawing research and soft dig utility locates be performed for known and identifiable utilities during the design phase. As a result, the risk of underground utility conflicts leading to schedule delays and construction claims is reduced. This also increases the clarity of the construction documents, which reduces risk to 79