Key Biscayne Master Plan 043944000.18w_Key_Biscayne_MP(forJooMag) | Page 101

9.0 TRANSPORTATION MANAGEMENT PLAN Guidelines for others that occupy the roads:    9.6 Landscapers and other contractors should be restricted to parking on roads without lane closures, or are outside the affected work area, unless otherwise approved by the Village Other contractors should be restricted to working on roads without on-going undergrounding work, unless otherwise approved by the Village Access to cyclists and pedestrians will be described in the construction documents for implementation by the contractor Conflicting Closures  No two adjoining corridors may be closed in the same direction at the same time  No two corridors that act as alternates to each other may be closed at the same time Notification, Coordination, and Approval of Closures  Contractors must notify the Village Engineer at least one week in advance of any proposed closures.  An internal Village of Key Biscayne communication representative shall coordinate all closure activity. This could be the Village’s project manager.  Any work requiring a closure will need to have an approved traffic control plan and corresponding MOT permit from the Public Works Department.  All approved closures must be communicated to the Village on a weekly basis by the contractor during the week prior to the closure so the Village can include traffic alerts on the Village website or undergrounding website. Traffic-Related Work Restrictions: The contractor shall maintain the same number of existing travel lanes and parking lanes in each direction open to traffic at all times, except as noted herein. Per the Village’s noise ordinance, the creation of any plainly audible sound in connection with construction is only permitted from 7:00 am to 6:30 pm Monday through Friday. Therefore, no construction activities are permitted during nights, weekends, and holidays. Weekdays  Mondays, Tuesdays, Wednesdays, Thursdays, and Fridays that are not Village holidays shall be considered weekdays. The day after Thanksgiving shall be considered a holiday. A “holiday weekend” shall be defined as the period between noon on the weekday before a holiday and noon on the weekday after a holiday.  The Village will produce a weekly media alert for traffic impacts for the upcoming week. At the discretion of the Village a phone number may be published in these media alerts that allows impacted motorists to call and report observed issues with the MOT operations.  Work will not be allowed on Village observed holidays.  The Village’s Public Works Department will coordinate closures among projects through the MOT permitting process and keep the community apprised of upcoming closure activities through media releases. Full Closures or Partial Closures  Full or partial closures will be allowed during weekdays.  A full closure of the main northbound and southbound thoroughfares will not be allowed at the same time.  Field personnel need to notify the Village Engineer and Design Engineer of any cancellations or changes in closure schedules.  A full closure of any travel lane(s) that does not allow the maintenance of two-way travel at all times will require the use of flag men during the closure period.   A full closure of any travel lane(s) that will create a one-way travel direction, or complete roadway closure, will require advance approval from the Village of Key Biscayne Public Works Department All roadway closures, material haul routes, and detours shall be approved by the Village of Key Biscayne prior to implementation. Material haul routes through the City of Miami and Miami-Dade County shall have appropriate agency approvals.  Contractor shall submit the details of the contemplated activities and related traffic impacts to the Village Engineer, City of Miami, 97