Ingenieur Vol.70 Apr-June 2017 ingenieur Apr-June 2017-FA | Page 80

INGENIEUR Damages for Late Completion In the High Court case of Sakinas Sdn Bhd v Siew Yik Hau & Anor [2002] 5 MLJ 498, the learned judge in coming to the conclusion that “no known measure of damages was employable” for delay claims said that “a complex cocktail of losses was involved, including financing charges, rental expenses, loss of profit and loss of use and enjoyment.” It is submitted that such losses, though difficult to prove and even more dif ficult to prove precisely, do not belong entirely to the category of losses for which there is no known measure of damages. At the most, such losses are a hybrid of the two types of losses postulated in Selva Kumar. In such a situation, it is difficult to see how a pre- determined sum can be accepted as the measure of the entire loss without any proof. Johor Coastal Development Sdn Bhd v Constrajaya Sdn Bhd The Federal Court re-looked Selva Kumar in Johor Coastal Sdn Bhd v Constrajaya Sdn Bhd [2009] 4 MLJ 445. Those in the construction industry, particularly employers, who still had a glimmer of hope that liquidated damages would be validated, were disappointed. In that case, a vendor and a purchaser entered into two sale and purchase agreements with identical terms in respect of two lots of land for RM4,590,000 and RM10,830,000 respectively. The purchase price was to be paid via six instalments. The purchaser paid the first three instalments for the two agreements totalling RM8,998,400 which included the initial payment of 12% amounting to RM 1,850,400 but defaulted in paying the balance purchase price. The vendor then terminated the sale and purchase agreements and forfeited the sums already paid. The purchaser applied for declaratory relief to the effect that the termination was unlawful and that the vendor was not entitled to forfeit all the sums already paid for being penalties which were unenforceable under s 75 of the Act. The vendor was granted leave to appeal to the Federal Court on the two questions posed: (a) whether the part of the decision in Selva Kumar which obliges a party having the benefit of a liquidated damages clause to prove its losses, 6 78 VOL 2017 VOL 70 55 APRIL-JUNE JUNE 2013 notwithstanding the words in s 75 of the Act “whether or not actual damage or loss is proved to have been caused thereby”, is correct; and (b) whether or not parties entering into a contract were entitled to contract out of the provisions of s 75 of the Act. The majority decision was to dismiss the vendor’s appeal. For the first issue, the court followed closely the dicta in Selva Kumar. The court held that the vendor could not “recover or retain without proof by evidence of the loss or damage suffered as a result of the breach of the agreements” because s 75 of the Act provided “that in every case, the court must determine what is reasonable compensation, ‘whether or not actual damage or loss is proved to have been caused thereby.’” The court agreed with Selva Kumar that actual damages or reasonable compensation must be proved. As for the second question, the Federal Court held, without giving any further reasons or elaboration, that the agreements did not clearly exclude the application of s 75 and that therefore it was unnecessary for the court to answer the question. Hence, that very crucial issue was skirted. Interestingly, the court referred to the case of Oil & Natural Gas Corp Ltd v Saw Pipes Ltd AIR 2003 SC 2629 and noted that nowhere there did the Indian Supreme Court state that the provisions of the Indian Contract Act could be contracted out of. This statement seems to imply that the Federal Court would not be inclined to hold that parties could contract out of s 75 if this question had to be answered. Contracting out of Section 75 of the Act A possible recourse for parties to have their genuine pre-estimate of loss being recognised by the court when awarding damages is to contract out of s 75 clearly and precisely. An authority on this exists in the form of Ooi Boon Leong & Ors v Citibank NA [1984] 1 MLJ 222. In that case, the Privy Council said that the legal consequences of a contract at common law are applicable unless some different legal consequences are spelt out by the Act. The Privy Council added, “The contracting parties are, however, not unable by agreement