Ingenieur Vol 62 April-June 2015 Ingenieur Vol 62 April-June 2015 | Página 48

INGENIEUR Brandon in The Bank of Boston case was ‘‘the same test in different language’’. Lloyd LJ held that for all ordinary purposes, the modern law of equitable set-off is to be taken as accurately set out by the Court of Appeal in Hanak v Green. He said that it is not sufficient that the cross-claim is somehow related to the transaction giving rise to the claim. The cross-claim and the claim must be so closely connected that it would be manifestly unjust to allow the plaintiff to enforce payment without taking the cross-claim into account. Simon Brown LJ in Esso Petroleum Co Ltd v. Milton [1997] 1 WLR 938 was of the opinion that the “mere fact that both claim and counter-claim arise out of a single trading relationship between the parties is … wholly insufficient to supply the close link necessary to support an equitable set-off.” After saying that the modern law of equitable set-off is to be found in Hanak v Green and The Nanfri, he restated the test as follows: For equitable set-off to apply it must therefore be established, first that the counterclaim is at least closely connected with the same transaction as that giving rise to the claim, and second that the relationship between the respective claims is such that it would be manifestly unjust to allow one to be enforced without regard to the other. That test is very similar to Lord Denning’s. The correct test for equitable set-off has recently gained the attention of the Court of Appeal in Geldof. Rix LJ considered the formulation by Lord Denning in The Nanfri, without any reference to the concept of impeachment, as the best statement of the test, and the one most frequently referred to and applied, namely: “cross-claims … so closely connected with [the plaintiff’s] demands that it would be manifestly unjust to allow him to enforce payment without taking into account the cross-claim”. In Permodalan Plantations, Salleh Abbas LP said that “if a cross-claim relied on by the defendant as a set-off does not and cannot absolve the plaintiff’s claim because it arises from a separate transaction, we agree that the cross-claim is not necessarily a set-off, though it is so described, and that such cross-claim could, because of its nature and quality, only amount to a counterclaim.” He added: 6 46 VOL 62 APRIL – JUNE 2015 VOL 55 JUNE 2013 It is, therefore, clear that a counterclaim is wider than a defence of set-off and that whilst the former is a separate action by a defendant against a plaintiff, the latter is essentially a defence, although a defendant is entitled to add it as counterclaim. Being a defence to a plaintiff’s action, the matter sought to be set-off must essentially be connected with or form part of the matter upon which the plaintiff’s action is founded. In Bukit Cerakah Development Sdn Bhd v L’Grande Development Sdn Bhd [2008] 3 MLJ 547, an employer was the developer of a project comprising two phases. It engaged the same contractor for both phases. For each phase, the employer and the contractor entered into a contract in the PWD form. After disputes erupted between the parties, the contractor filed two separate suits against the employer in respect of the two phases. In the Phase 2 suit, the contractor claimed for sums due under interim certificates. The employer met this by a defence and counter-claim alleging fraud, breach of contract and negligence by the contractor. In his counterclaim, the employer claimed a sum of RM46,210,924.68 for reason that 243 out of the 331 units lacked structural integrity and had therefore to be demolished. For this purpose, it relied on interim certificate 14 issued by the architect. In the Phase 1 suit, the contractor claimed for the sum of RM3,665,582.94 purportedly due on interim certificates. The employer put up a defence and counter-claim to the contractor’s claim. Among the pleas taken, the employer sought to set-off monies owing from the contractor to the employer under the Phase 2 contract against any sum that might be due from the employer to the contractor under the Phase 1 contract. The employer relied on clause 50 of the Phase 2 contract for his right to a set-off. The Court of Appeal stated as follows: The starting point is the general law regarding the defence of set off in the context of a building contract. It is a principle of general application that both an employer and a builder have a right of set off against each other in the absence of a contrary intention expressed by the parties. Such a contrary intention may appear from express words used by the