Ingenieur Vol 62 April-June 2015 Ingenieur Vol 62 April-June 2015 | Page 46

INGENIEUR had alleged defective work and challenged the correctness of the certificate. The pivotal issue that called for decision there was whether, upon the true interpretation of the building contract, an obligation rested on the employer to pay the sum at once without regard to pending disputes including cross-claims by the employer. The Supreme Court had to consider whether it was available to the employer to rely on his claims for liquidated and non-liquidated damages to defeat the builder’s claim. It is noteworthy that the architect had not invoked his powers under the building contract to direct the builder to do rectification work in response to the employer’s complaints of defective work, materials and/ or over-valuation. In the event, the builder was under no obligation to remedy the deficiencies complained of. The court said that “the express enumeration of permitted set-offs in a contract or sub-contract, can imply that a defendant builder or main contractor, as the case may be, is limited to making such deductions from the amounts claimed as fall strictly within the scope of the permitted set-offs, and nothing else, on the basis of the expressio unius principle [a maxim of interpretation meaning that the expression of one thing is the exclusion of another].” Applying this principal, the contended set-off by the employer did not fall into any of the seven permitted categories of set-off in the contract. The Supreme Court held that the employer’s alleged right to a set-off had “been extinguished, not expressly but by clear implication”. In Dataran Rentas Sdn Bhd v BMC Constructions Sdn Bhd [2008] 2 MLJ 856, the appellant and respondent had entered into a construction contract in the form of the PAM Standard Form Building Contract 1969 Edition (Without Quantities). The appellant failed to make payment to the respondent for amounts due under four interim certificates within the stipulated time. The respondent then determined the contract. The appellant alleged that the determination was wrong and that there were defective works. Relying on the dictum in Pembinaan Leow Tuck Chui that the right of set-off is restricted to those expressly allowed under the contract, Zulkefli JCA found that the appellant had no right of set- 6 44 VOL 62 APRIL – JUNE 2015 VOL 55 JUNE 2013 Engineers at a project site. off under the PAM contract against the certified sum. There was no architect’s instruction issued under clause 2(1) that the works carried out by the respondent were defective. In the unpaid interim certificates, the architect had stated: “Addition/ Deduction for works not in accordance with the contract” as being “RM nil”. A widely drafted clause forbidding a set-off, deduction or withholding may well be able to exclude reliance on any claim to pay less than the full amount, whether that claim is based on a “pure” defence, abatement, set-off or counterclaim (Totsa Total Oil Tradi ng SA v Bharat Petroleum Corp Ltd [2005] EWHC 1641 (Comm)). EQUITABLE SET-OFF It is generally agreed that the modern law of equitable set-off dates back to Hanak v Green [1958] 2 QB 9 with Morris LJ’s judgment being described as “authoritative” by Dillon LJ in BICC v Burndy Corporation [1985] 1 Ch 232 and “masterly” by Lord Diplock in Gilbert-Ash. Under this doctrine, the court could intervene to restrain someone who had commenced an action at law from proceeding with the trial of the action or from levying execution of a judgment until further order. The circumstances include the existence of an un-liquidated cross-claim by the defendant and regarded by the court as justifying the protection of the defendant from the plaintiff’s claim. An equitable set-off operates in a litigation to extinguish the claim and prevent its original establishment, rather than to provide a sum to be netted off against the claim once established. Morris LJ in Hanak v Green identified two factors as being critical in qualifying a crossclaim as an equitable set-off: it would have been