IN West Jefferson Hills Summer 2018 | Page 43

regain some of the footing lost in the schedule and that we could still get in on time. We requested a recovery schedule in November and have done so since that time but have yet to officially receive one. During December, there were days when we had as few as four roofers and twelve bricklayers on the project, even though we were told more workers were available through the union hiring halls. Since then, many major milestones were missed and the schedule has continued to slide. We knew coming out of February that getting into the building by September was a long shot. It was at that point that we began to plan for a Thanksgiving move-in date which was reflected by adding an additional day to Thanksgiving break in the 2018-2019 school calendar that was approved by the school board in March. Thanksgiving seemed both reasonable and logical given where we were on the project, although the district was not presented any sort of recovery plan until May 2018. Because of this slide, the project is now further behind. Since the project is out of sequence, it has now become a phased project. Most of the classrooms are dry walled, painted, and receiving casework. However, the theatre and arts classrooms just had their cement slabs poured at the end of May. We have had many meetings with our construction manager (Turner Construction), general contractor (Nello