Firestopping Book Firestopping Book | Page 124
JOINT SYSTEMS | UL Product iQ
Page 3 of 3
wall shall be packed with additional strips of mineral wool batt insulation compressed 33 percent in thickness flush
with the surface of the wall.
ROCK WOOL MANUFACTURING CO — Delta Board
D. Fill, Void or Cavity Material* — Min 1/8 in. (3.2 mm) wet thickness (min 1/16 in. or 1.6 mm dry thickness) of fill
material sprayed or troweled to completely cover mineral wool forming material and to overlap a min of 1/2 in. (13
mm) onto wall and steel deck on accessible side of the wall.
HILTI CONSTRUCTION CHEMICALS, DIV OF HILTI INC — CP672 Firestop Spray or CFS-SP WB Firestop Joint
Spray
* Indicates such products shall bear the UL or cUL Certification Mark
for jurisdictions employing the UL or cUL Certification (such as
Canada), respectively.
Last Updated on 2010-06-04
The appearance of a company's name or product in this database does not in itself assure that products so identified have been
manufactured under UL's Follow-Up Service. Only those products bearing the UL Mark should be considered to be Certified and
covered under UL's Follow-Up Service. Always look for the Mark on the product.
UL permits the reproduction of the material contained in the Online Certification Directory subject to the following conditions: 1.
The Guide Information, Assemblies, Constructions, Designs, Systems, and/or Certifications (files) must be presented in their entirety
and in a non-misleading manner, without any manipulation of the data (or drawings). 2. The statement "Reprinted from the Online
Certifications Directory with permission from UL" must appear adjacent to the extracted material. In addition, the reprinted material
must include a copyright notice in the following format: "© 2019 UL LLC"
(Fig 4.18)
INSTALLATION AND INSPECTION
The inspection of penetration firestops and joint systems is not
specifically addressed in the code. As a general rule, these are
“listed” systems and therefore must be installed in accordance
with their listing and the manufacturer’s installation instructions.
Code users may want to be aware of the ASTM E 2393 standard,
Standard Practice for On-Site Inspection of Installed Fire-resistive
Joint Systems and Perimeter Fire Barriers. According to Chapter 17
(see Sections 1705.17 and 1705.17.2), compliance with that standard
is mandatory for special inspections of fire-resistant joint systems
where required. A brief discussion of this standard is included at the
end of this book in the section dealing with miscellaneous topics.
https://iq.ulprospector.com/en/profile?e=170318