e-mosty September 2018 Vessels and Equipment Used for Bridge Construction | Page 55

DRY AND WET DOCKS Dry dock Dry dock construction works comprised the following:           Construction of retaining bund and revetments for both the temporary and permanent sections. Driving sheet piles. Dewatering & Excavating of the existing land down to specified bottom level of the dry dock. Compaction of bottom of dry dock area. Provide surface drainage system. Road construction. Dredging of approach channel. Removal of temporary bund. Final sweep. Final removal of temporary bunds & dry dock Dredging for the approach channel trenches was performed from the offshore end towards land by dredging equipment, mainly by back-hoe dipper dredger and split dump barges, see Figure 2. Construction of the wet dock comprised pile driving works, RC plugs, in-situ deck slabs, installation of steel catwalks and installation of a tower crane. The piles were loaded on the barges using a crawler crane. The service barge was then towed to the offshore construction site using tugboats. The tower crane was installed using a floating crane. Two tower cranes had previously been installed on the caissons in the dry dock. TOWER FOUNDATIONS The sequence of marine construction works for the North and South Tower Foundations was as follows: 1. Dredging, transportation and disposal of dredged material. 2. Inclusion piles. 3. Gravel bedding. 4. Caisson Construction. 5. Steel Shaft Installations. 6. Caisson towing and installation. 7. Plinth and tie beam construction. 8. Scour protection. Dredging, transportation and disposal of dredged material In order to create safe navigational channel, temporary navigational buoys were installed at the determined coordinates using the “Yaşar Doğu-I” Anchor Handling tugboat. A marine emergency response plan was followed in order to prevent ship collision. Figure 2: Dredging in front of approach channel and underneath of dry dock retaining bund After the dredging operations, a final sweep was done using a harrowing technique, which involved towing an I- Beam behind the ocean going tugboat “Yaşar Doğu-I”. Wet dock A temporary wet dock was constructed at the South of an existing lagoon in Hersek Peninsula to berth the tower foundation caissons for the completion of second stage concreting works, installation of the steel shafts and precast top slabs under the in-situ concrete top slab. 3/2018 Figure 3: Installation of navigation buoys