e-mosty September 2018 Vessels and Equipment Used for Bridge Construction | Page 53

SUBSTRUCTURES The North and South anchorages are triangular shaped gravity structures with cable anchorages and transition piers. The South anchorage also has a side span pier on the anchorage. Before placing the tower caissons, the following activities on the sea bed were completed at each tower location:  Dredging: 3 meters of sea bed surface material was removed using a clampsell dregder.  Inclusion Piles: 195 two meter diameter hollow inclusion piles with a length of 34.25 meters were driven by underwater hydro hammer.  Gravel Setting: A layer of gravel was placed by a tremie pipe and levelled using a special underwater hydraulic levelling frame. Caisson foundations for the towers were prefabricated in a dry dock and a wet dock, and the circular steel shafts that ultimately support the tower legs above, were fabricated at a nearby shipyard. The following activities were completed for each caisson:  Dry dock works: A temporary dry dock was made before official commencement of works, and concrete for the lower part of caisson (almost 3/4) was cast after official commencement.  Towing to wet dock: The caissons were then towed from the dry dock to the wet dock via a dredged channel.  Wet dock works: The remaining concrete was cast on the floating caissons and two steel shafts were erected on each caisson. The steel shafts were fabricated at shipyard close to the site and delivered to the wet dock by floating crane.  Caisson sinking: The caissons were filled with sea water and sunk at each tower location within a 200mm tolerance in X and Y planes.  Plinth & Tie beam: The concrete plinths and tie beams at the top of the steel shafts were cast, incorporating the anchor frame for the steel tower. Figure 5: Diagram of South Anchorage Block The tower foundations are concrete caissons placed at - 40 m below sea level on a granular material supported by improved soil with steel inclusion piles. Figure 6: Diagram of caisson 3/2018