e-mosty September 2018 Vessels and Equipment Used for Bridge Construction | Page 44

Design and preparatory works The construction process to assemble the cable- stayed bridge section consisted of consecutive deck sections lifts, by means of the balanced cantilever method. Typical sections measured 20m long x 34.3m wide x 2.7m high and the weights varied between 150t and 405t. Using the strand jacks, the deck sections were lifted and welded into position. Then the travellers moved 20m forward (the typical length of each section) for the following deck section lifting manoeuvre. Transport and lifting of the cabled sections - equipment and operations The lifting operations took place at the quay of Cabezuela in Puerto Real, Cádiz. In order to lift the deck sections, ALE designed four lifting travellers (two per main pier) which were placed on the 52m-long deck section that was previously installed, as this is the minimum required length to install the lifting trolleys. Figure 3: Installation of travellers These were moved by skidding along rail beams, which were previously launched using two 500t capacity skid shoes located on the central frame and through the bogies (working at the back frame), into position. Figure 2: Traveller Each lifting traveller comprises two longitudinal steel lattices measuring 50m, which were transversely separated one from the other by 20m. The traveller was supported longitudinally onto the deck section in its first 20m, leaving 30m of cantilevered lattice. The rear support, working under tension, connected to the bridge through pre-tensioned bars, whereas the front part was working primarily in bending. Note that the final deck section included a top precast concrete slab. However, two different lifts were performed at every stage: the first one for the steel part of the section and the second one for the concrete slabs. The first lift was critical in terms of maximum weight to lift, whereas the second one was critical in terms of maximum overturning moment for the traveller. Over these cantilever sections two transverse trolleys were installed, including two 200t strand jacks each, moved by means of a skidding system of 150t capacity, which comprised flat skid beams and push - pull units. The trolleys allowed for both adjustment for the location of the lifting units to the centre of gravity of each section and adjusting the final location of the section before welding the bridge. 3/2018 Figure 4: Lifting of a section