e-mosty June 2018 American Bridges American Bridges | Page 50

The design of this structure over the Ottawa River presented several major challenges, including environmental constraints, the proximity of the existing bridge and the presence of a geological fault at the bridge. During the design phase, the option to reduce the number of piles in relation to the existing bridge was chosen by the owner as this limited the environmental impacts of the project. Optimization of the concept led to the choice of a variable-inertia steel caisson bridge, continuous over three spans, including a main span of 10 meters and two 85-meter bank spans. Considering the location of the bridge and the tight construction schedule, a steel structure had the double advantage of being able to be quickly built in fabricator plants and then transported by truck for assembly during all year periods. The use of beams with variable inertia, in addition to allowing the optimization of the use of the material, gave a slender and harmonious aspect to this large structure. The presence of a geological fault at the right of the structure represented an important stake during the design. As a result of multimodal modeling and seismic analysis of the bridge, caisson piles with rock socket were retained for the pile foundations. Seismic isolators were incorporated to reduce the impact of an earthquake on the structure. In addition, special control measures had to be taken to ensure that the sockets of the caisson piles had the necessary length to withstand the forces while remaining in the sound rock zone, without encroaching on the shear zone of the fault characterized by a highly fractured rock. The main beams were erected using a combination of conventional methods and atypical methods: the edge spans were erected from temporary piers, using mobile cranes and temporary piers, while the assembly the central section of 90 meters in length was made by jacking the two box beams simultaneously from a barge. Since the structure is continuous, the beams had to be lifted about 1.3 meters to the abutments to achieve geometric compatibility allowing the bolting of construction joints. 2/2018 The required erection method involved the use of a 400-metric-ton crawler crane, temporary supports, several jacks, and a 1.3-meter abutment lift to connect the splices in the center section. The use of a steel frame was the large contributor to the success of the project, which was completed in less than 18 months, the main assembly of the structure was done in the heart of winter, thereby saving precious months, without stopping work. Once the bridge was fabricated, the team entered a time trial race with the general contractor to complete the assembly before the spring breakup. Given the bathymetry conditions of the Ottawa River at this location, a temporary barge bridge was put in place, making assembly of the structure more complex. To respect the schedule, it was decided in the preliminary draft not to fabricate the structure in a linear way as usual, but rather to manufacture the box girders according to the assembly order desired by the general contractor. This required particular logistics during the fabrication of the components, which made it possible to deliver the beams in time. The design team was also forced to adapt to the singularity of this project by partitioning the shipment as soon as the drawings were approved to allow for a rapid production. The weight of some beams reached more than 90 tons, exceeding the lifting capacity with the fabricator’s plant, therefore Engineers were asked to find a solution for moving these parts. The team of experts therefore set up a system consisting of hydraulic cylinders and rollers that made it possible to slide each of the boxes out of the factory without having to use the cranes. Beams were shipped to the site, as soon as the fabrication was complete, so as not to delay assembly. Challenges were even more complex than anticipated, as some restrictions issued by the Department of Transport, such as height, weight, or certain traffic barriers due to construction, were not known at the outset. All challenges were met and the project was successfully completed.