Construction of beam arch combination bridge
After incremental launching of continuous box beam,
the steel tube was constructed on the top of deck
system.
Bailey girder trusses were used for the temporary
support system, and the steel tube was rotated
vertically for the main arch ring closure.
Concrete was placed in the steel tube using a
concrete pump machine, as shown in Figure 27.
The main arch ring and continuous box beam were
connected by 28 suspenders, each one was composed
by 18no. 7 strand 7mm parallel wires with 4900 kN
initial tension force.
Figure 27: Main arch bridge construction process
After concrete filled steel tube main arch ring was
completed, each suspender was tensioned to design
force, causing the box beam to lift up and disconnect
from the construction temporary piers, as shown in
Figure 28.
Figure 28: Completed main arch
REFERENCES:
CHINA TECHNICAL CODE FOR CFST ARCH BRIDGES
B.C. Chen, J.G. Wei, Q.X. Wu
College of Civil Engineering, Fuzhou University, Fujian, 350108,
CHINA
APPLICATION OF CONCRETE-FILLED STEEL TUBE ARCH
BRIDGES IN CHINA
J. Wei, J. Zhou, J. Liu, B. Chen
College of Civil Engineering, Fuzhou University, Fuzhou 350108,
CHINA
CONTINUOUS DESIGN OF CANTILEVER BEAM OF CFST
HALF-THROUGH ARCH BRIDGE
1
1
2
2
2
3
X. Zuo , X. Liu , L. Ren , S. Tan , G. Shang , W. Li
1
Hunan road & bridge construction group Co., Ltd, Changsha
410004, CHINA
2
CCCC FHDI engineering Co., Ltd., Guangzhou 510230, CHINA
3
Shaoguan public utilities board, Shaoguan 512031, CHINA
RESEARCH ON A CFST TIED ARCH BRIDGE CONSTRUCTED
BY INCREMENTAL LAUNCHING METHOD
1
1
2
2
3
J. Huang , J. Shi , X. Shangguan , C. Hu , Z. Dai
1
Fourth Harbor Engineering Investigation and Design Institute,
Guangzhou, CHINA
2
East China Jiaotong University, School of Civil Engineering and
Architecture, Nanchang, CHINA
3
China Railway Fourteenth Civil Engineering Group, Jinan, CHINA
GB 50923-2013, China National Standard-- Technical Code for CFST
Arch Bridges
(In Chinese), 2013
All papers were presented at 8th International Conference Arch
2016: Arch Bridges in Culture, which was held in Wroclaw in Poland,
from 5th to 7th October 2016. They were published in a book of
papers from the conference.
OTHER REFERENCES:
COLLINGS, David: Steel-Concrete Composite Bridges.
ICE Publishing 2013
4/2018