e-mosty December 2018 e-mosty December 2018 | Page 45

For these manoeuvres, ALE utilised barges on the Swan River to float the wishbones to the designated piers and used the Mega Jack as temporary 50m high towers to pull the wishbones up. After successfully lifting the first wishbone using strand jacks, the second wishbone was lifted and concurrently the both wishbones were successfully docked within two weeks’ time. The fourth stage was the lifting of the five bridge decks, which formed the pedestrian and cycle path crossing the river. III. SPMT TRANSPORT The two wishbones were transported from the assembly area onto the barges using SPMTs. The SPMTs were prepared under ALE supervision in the required configurations, and temporary supports were installed and lashed on the trailer deck. Following the assembly, the trailers were positioned under the wishbones and concurrently transported to the quay side for load-out. As the two wishbones had a unique design, the configuration of the temporary supports was changed under ALE supervision allowing the trailers to be positioned and the wishbone to be transported for load-out. IV. MARINE TRANSPORT The marine transport was executed using two barges. These barges were connected with a truss system causing the barges to act as a single floating system. V. INSTALLATION OF MEGA JACK TOWERS During the SPMT and the water transportation, ALE personnel executed the installation of the Mega Jack system concurrent on each pier. The main structure of the Mega Jack system and the lifting construction was built as low level as possible. This was to reduce the amount of heavy crane works required, and, more importantly, to reduce the amount of working at height hours. Following the installation of the Mega Jack system, the towers were individually jacked-up to a height of 65 m above the level of the assembly area of the wishbones. After docking the wishbone(s), the strand wires were connected from the top lifting construction with the wishbone(s) using Dyneema slings. This gave the necessary flexibility, eased the connections of the strand lift system, and reduced lead times required for connections. Finally, the main lifts were executed and each wishbone was lifted to an over rotated stage to allow the final docking of the wishbones to take place. The final docking took place with a strand jack operator on each side of the river, which were able to lower the wishbone(s). The full connection in the top of the wishbone was established using camera systems and geometrical survey. VI. INSTALLATION OF THE BRIDGE DECKS The load-out followed the pre-determined procedure which involved coordination between three parties and the use of crawler cranes and SPMTs. Concurrent the final docking of the wishbones, the barge system was floated back to the assembly area. There, the old transport construction was modified and the barges were connected together. When the load-out was completed, all mooring lines were installed to allow the float-in itself to commence. This allowed the bridge decks to be lifted on top of the new barge system using a 650t crawler crane. Due to the assembly restrictions, one of the wishbones required a 180° rotation on the water, which required the repositioning of all mooring lines during this rotation. Following the float-in of each wishbone, the wishbones were docked on their designated foundation and secured for unwanted movements. As no ballasting of the barges was involved in any of the operations, the tidal compensation and any required height changes for docking were executed by using hydraulic cylinders. These were able to lift and lower the wishbone individually on each barge. 4/2018 In the new barge system, also hydraulic cylinders were present to overcome any barge draft and compensate tidal levels. The bridge decks were floated one by one under the main arch and connected to the cables hanging from the arch. After installation, each bridge deck was lifted individually to allow the pretensions adjustment of the cables. When all works were finished, all equipment was removed from the site and demobilised.