e-mosty December 2018 e-mosty December 2018 | Page 42

This situation has the potential to impose substantial risk on the constructors and designers which could have been avoided through an Alliance form of con- tract. In this instance, the proposed use of gantry cranes to install the new steel box girders from the existing viaducts was a key decision which acted as a con- straint on the remainder of the design. The limited capacity of the existing viaduct cantilevers, and to avoid the need to strengthen them, constrained both the local wheel loads from the gantry and the weight of the new box girders. As the gantry cranes were also used to install the formwork for the pier crossbeams, the designers un- dertook considerable analysis to maximise construc- tion flexibility, whilst respecting the weight limit pa- rameters. Temporary cantilever props were required at each end of the bridge where the gantry crane wheel loads would not be able to distribute loads into the cantilever in both directions. COMMENTARY ON WIDENING PROVISION VERSUS DEMANDS The widening scheme utilised all provision made by the original designers, making the provisions a suc- cess. However, access for construction and launching of the originally envisaged scheme would have been difficult under current traffic closure constraints, and replacement of bearings under traffic load was not anticipated. This required some local strengthening of the pier tops to be undertaken in advance of the main works. More generally, the higher traffic and seismic loading of current design standards was not anticipated. Provision for future widening was less pronounced in the 130m concrete approach structure. Although the concrete slab did not make direct provision for con- nection of the new deck, and the expansion joints were not aligned, a widening scheme was achieved to match the existing structural form. LESSONS FOR THE FUTURE This article provides an interesting example of how this structure withstood the demands of time and upgrade work in order to meet today's transportation demands. Together with experience of maintenance and up- grade works on other bridge structures, the authors propose the following lessons for the future: 4/2018 1. Limitations of Code Compliant Design While bridges are designed to the codes in force at the time, Code Compliant Design is not a guarantee that the bridge will see through its service life with no problems. Unanticipated behaviour can still occur. Codes and standards are, through necessity, a simpli- fication to reduce a range of details and behaviours down to a level where they may be represented by rules and equations. Design innovation and constraint are increasingly necessary in modern design, but the research and testing behind the codes becomes more distant and inaccessible to the engineer. This may permit the de- sign of details which were not adequately covered, or were beyond the intent of the original research. Research and testing can also become dated, and therefore may not adequately reflect the current transportation and environmental conditions, or cur- rent construction methodologies. Engineers should have greater access to this research to be able to make an informed decision on its adequacy. Where the codes and current research do not provide sufficient authority, engineers need to acknowledge and promote the need for further testing and re- search for novel or unusual features at design stage. Clients and Owners must understand and recognise the value of this additional testing or research. Prototypes, including full scale mock up modules, can provide immense value to a project, and sufficient time and funding must be allowed. 2. Future provision versus retrofit In the case of EJ Whitten, the provision made for the future was largely successful, albeit narrowly so, con- sidering the increased demands of current loads. The lesson here is to anticipate future demands and aim to build in sufficient reserve beyond that for the inevi- table changes that will occur. Although it is not always possible to predict the fu- ture, trends are usually evident and provide a good basis for prediction. The most economical time to provide modest additional capacity is at the time of original construction. In our experience of retrofitting, it is often very com- plex and heavily constrained. With a modest degree of additional foresight by the original designer and owner, retrofitting would be made easier and more cost effective.