     A harp arrangement of stay is used to give uniform stay sizes which rationalises the types of saddles and anchorage details. The stay cables are replaceable and, to the detail, filled with foam at discrete locations to prevent the vibration of the HDPE duct against the strands. Unusually I developed asymmetric prestress within the towers to counter the torsion in the deck and cater for a range of stress states in construction and in the permanent condition. The crossbeams at the towers carry significant structural forces and cope with different deck geometries at each pier. The dramatic curve and detail of deck connection with the beam offers needed stiffness whilst minimizing the visual impact and gives interest and clarity when viewed from underneath. The cross beams are prestressed to cope with erection and permanent loads and are designed to be robust enough to be used as bases for tower cranes to minimise the size of crane required. Prestressed earth anchors tie the pilecaps into the bed rock to provide a sufficiently-robust foundation under seismic loads. In an environment where economic factors often produce uninspiring structures with brutal short spans and simply supported precast beams on bearings or in-situ concrete box girders – the Wadi Abdoun Bridge is unique. I utilised my experience in design and engineering to give efficient and economical construction. I believe that the bridge stands as a landmark of quality and excellence for Jordan’s capital city. Balanced cantilever erection over the arterial road at the base of the valley give safe construction over a busy live road using bespoke gantries. 3. CLARITY OF THE STRUCTURAL FORMS I believe that the forms of structural elements adopted for any particular project are integral with and inseparable from the concept design. The development of the type of bridge deck, supporting pier, rationalisation of long span structures, precasting for achieving quality, economy and durability and construction technology are then all considered at the concept stage. 4. SIMPLICITY IN CONSTRUCTION The construction method often dictates the economics of the structure, but with the emergence of the privatisation of infrastructure projects some of the criteria hitherto ignored are assuming greater importance. In particular, the construction time should be as short as possible, quality should be guaranteed and above all the structures should be constructed with simplicity and minimal risk. In arriving at the total cost of the project, the material cost must be considered together with the time required for construction. Thus the material cost of structures taken alone is not of overriding significance now that market forces have also placed the engineer in a managerial role to conceive and deliver a complete project on time and on budget. 2. NEED FOR KNOWLEDGE ON SITE & CARE The buildability of the structure was an important consideration in the concept, especially given the limited local experience with this structure type. The bridge is also a complex structure to construct, with large cantilevers deforming in three dimensions and to be accounted for with the deck and tower precamber. Further complexities include super elevation and the effect of staged stay stressing on a curved deck. I personally guided the contractor through these issues adding value above and beyond the contractual requirements to enable the project to be completed successfully. 4/2018 Figure 5: Night view with stay lighting