e-mosty December 2017 MSS and Formwork Travellers | Page 26

Figure 10: Opatovický Kanál Figure 11: Sokolov – Tisová Viaduct 2. Projects 2.1.2 Bridge across the River Váh's Reservoir Hričov, section Žilina-Strážov - Brodno, Slovakia 2.1 MSS M45-S, Slovak Republic The MSS M45-S was developed for the construction of a motorway viaduct between Sokolov and Tisová and for a bridge across Opatovický Kanál, both in the Czech Republic, and again later for the construction of viaducts between Poprad and Prešov in the Slovak Republic. In 2017 it was also used for a motorway viaduct on the D3 highway between Strážov and Brodno in the Slovak Republic. The bridge is part of the D3 motorway project near the city of Žilina. The twin bridge with a total length of 1.5km is formed by a continuous structure of span lengths from 30.5 to 110m. The left viaduct has 9 spans of 44m. The right viaduct has 8 spans of 44m, 1 span of 38.3m and 1 span of 27m. 2.1.1 Description of the MSS It is an overhead MSS with an organic prestressing system (OPS) for spans of max. 45m and max. deck width of 14m. It comprises a steel truss with a top arch. Typical performance cycle is 10 days. Formwork for this project was modified in cooperation with its supplier due to the proximity of the decks and the radius of curvature on plan (low and variable). The construction period was 48 weeks. The MSS allowed the client its reuse. Figure 12: Location of the bridge Source: Google Maps Figure 13: The MSS is ready for launching 4/2017