of the transverse girders. Grade 460 high strength steel was adopted for the clevis plates and hemispherical bearings were also incorporated to enhance the out-of-plane rotational capacity, thus providing greater installation tolerance. The installed north bank arch nodes, the ties and the temporary props are shown in Figure 5. At the same time the ladder deck is assembled on the temporary supports, the arches and bracing will be assembled on the south river bank. Following completion of the installation of the ladder deck steelwork, the arches and the plan bracing will be installed via a tandem lift by two large cranes from the river bank. The arches will be offered to the end nodes in a prescribed sequence. Temporary tie cables will be used to control the shape of the arches to facilitate accurate placement. Once the site joints are welded, the hangers will be installed and stressed in a prescribed sequence. The “piecemeal” erection methodology induces bending moments in the tie beams that are generally avoided in network arches. In order to minimise the magnitude of these moments, the stressing of the hangers will commence as soon as the structural steelwork is erected, before the installation of the permanent formwork and deck. This first phase of hanger stressing will relieve the temporary works and it will transfer the gravity loads in the arches and the tie beams. The hanger installation and stressing pattern is aimed at avoiding “slack” hangers in working conditions. The stressing will commence from the centre outwards so that the temporary towers are relieved after the first few stressing operations. Once the first phase of stressing is complete the concrete deck will be constructed in sections. Following the initial cure of the deck slab a second phase of hanger force tuning will be applied so that the target in-service performance of the hanger network is achieved. It is worth noting that the construction sequence was refined on a number of occasions to suit various site parameters and this has led to extensive discussions between the designers, the fabricator and the main contractor and their cooperation was key in the successful and practical step by step construction methodology. Fig. 5: Current construction stage 4/2016