e-mosty 4 2016 Arch Bridges | Page 46

Fig. 2: Rendering of the bridge 1.4. Other Elements The deck is supported by spherical bearings except at the fixed point, where the arch is monolithically linked to the deck. Box abutments with intermediate walls are designed with maximum heights of 8.63 m at one end and 9.64 m at the other. The bearings and expansion joint devices are supported by these. Environmental issues with birds made it necessary to use railway edge barriers 3.00 m high. The barrier is formed by steel curve tubes 100 mm diameter every 0.50 m. In the lower part longitudinal horizontal tubes with differing diameters are used. The aerodynamic behavior of this barrier was tested with satisfactory results. 2. CONSTRUCTION PROCESS 2.1. General definition of the deck construction The deck is built by a movable scaffolding system, consisting of a steel truss. The steel truss is supported by two adjacent piers, this being the chosen for method every span of the viaduct. To avoid excessive stresses in the arch, the erection of the spans over it was symmetrical. The deformation of the arch and an interaction between the elements of the bridge was considered in the design. 2.2. General definition of the arch construction The arch is erected from both sides of the bridge concurrently, and was supported by diagonal cable stays strung from the adjacent piers and two steel temporary towers. The towers were in turn stayed to the foundations of the next two piers as they needed to be anchored to the ground to withstand the loads exerted by the stays. For each semi-arch, several auxiliary elements are needed: A steel tower was placed over the piers and; a form traveler system. A group of cable-stays was 4/2016 used to support the built part of the semi-arch, it was anchored to the tower and piers to maintain the equilibrium of the tower. The pier was anchored to the foundations and the foundations in turn anchored to the ground. Each steel temporary tower was composed by two columns at a distance of 6.50 m joined by a K bracing. The section of each column is a hollow steel box. The tower width is reduced where the tower meets the deck, to allow a correct transmission of the loads to the pier top. The bracing system is composed of horizontal beams placed at 4.00 m spacing and diagonal elements that form a K turned 90 degrees. The bracings were steel double T fabricated cross sections. The form traveler system was also a steel structure designed to support the formwork of each arch segment which allows the concrete to be cast in place. It was a cantilever structure, with a weight of 95 tonne attached to the already executed and hardened part of the arch. The arch is composed of 93 segments each about 3.80 m long. Regarding the cable-stayed system, 15 pairs of stays supported each semi-a rch and another 15 pairs held each tower. A pair of stays was placed in the arch every three segments. Tower cranes: Materials (reinforcing bars, concrete and prestress) were taken to the form traveler system through two tower cranes installed on each semi-arch. As in other major infrastructure projects, auxiliary structures are key to the satisfactory completion of the works. The project had a system of four tower cranes and temporary stairs to access the 70 m high