Summary Transportation Improvement Program - Carryforward Amounts
Program Period: Fiscal Years 2013 to 2018 - Starting 12/1/2012
Selected: All
6-Year
Total Cost
Project Description
E-00553a
Cedar Lake Rd (1 of 3)
IL Rte 120 to IL Rte 60
Roadway
Expansion
Stage 1: 2 lanes IL 60 to Town Line Rd
E-00553b
Cedar Lake Rd (2 of 3)
IL Rte 120 to IL Rte 60
Roadway
Expansion
Stage 2: 2 Lanes - Town Line Rd to IL Rte 120
E-00553c
Cedar Lake Rd (3 of 3)
IL Rte 120 to IL Rte 60
Roadway
Expansion
Stage 3: 4 lanes
Project Totals
B-00838
Center St
@ IL Rte 83
Intersection
Modernization
County Share of IDOT Add-Lanes Project
Project Totals
D-00372
Center St
@ US Rte 45
Intersection
Modernization
County Share of IDOT Project (C-91-208-00)
Project Totals
D-00605
Center St
IL Rte 83 to US Rte 45
Resurface
Preservation
Resurfacing
Project Totals
$0
Jun-2006
$793,300
$793,300
$4,100
Aug-2011
$0
$0
Oct-2019
$793,300
$793,300
$4,100
$100
$100
$0
$100
$100
$0
$13,400
$13,400
$0
$13,400
$13,400
$0
$1,374,000
Worktype/Cat
$0
$0
Route/From-To
6-Year
County Cost
$0
PIN
6-Year
County Revenue
Program
Date
$1,374,000
$0
$1,374,000
$1,374,000
$0
Jan-2019
Jul-2010
Jan-2016
B-00859a
Central Lake Thruway (1 of 2)
US Rte 12 to US Rte 41
Roadway
Expansion
IL Rte 120
$0
$0
$0
Feb-2019
B-00859b
Central Lake Thruway (2 of 2)
US Rte 12 to US Rte 41
Roadway
Expansion
IL Rte 120
$0
$0
$0
Feb-2019
$0
$0
$0
Project Totals
D-00552a
Chain OLakes Path (1 of 2)
@ Grant Woods FP
Bikepath
Modernization
Underpass to Connect the 2 Sections of Grant
Woods Forest Preserve
$824,700
$824,700
$0
Jan-2007
D-00552b
Chain OLakes Path (2 of 2)
@ Grant Woods FP
Bikepath
Modernization
Underpass to Connect the 2 Sections of Grant
Woods Forest Preserve
$0
$0
$0
Jan-2007
$824,700
$824,700
$0
$5,900
$5,900
$0
$5,900
$5,900
$0
Project Totals
B-00779
CMAP Assessment 2014
Plan
Expansion
Annual Assessment
Project Totals
U:\CPMS2000\cpmsdata\FY1318\CPMS Files\fy1318_6c.mdb - Ver. 6c, 6/13/2013 6:28:44 PM
Page 8 of 60
Jun-2013