City Manager's Bi-Weekly Report Volume 2 | Issue 5 | May 2018 | Page 16
Parks & Recreation
Pictured Above:
Strategic Plan Staff Retreat
Major Projects
District 1
• As part of the Capital Improvement Projects approved for FY 2017-
2018, Davco Electric, Inc., installed an interior and exterior lighting
system to improve overall security at Sportsman’s Park. Project
was completed April 17, 2018.
District 3
• City-approved vendor performing maintenance and cleaning of
gutters, Minsky Gym, Tuesday, May 1.
District 4
• At the Community Center, Davco Electric, Inc., will be running
power to the shed and to the pond. Project will begin 4/18/18.
• Community Center –new carpet installation for Rooms BCD i n the
banquet hall was completed on Friday, April 27.
• Specialized Fitness Resources will be installing new flooring in the
Humana Fitness & Wellness Center as well as in the Community
Fitness & Wellness Center, beginning May 14 and anticipated to be
completed on May 21.
15