Campus Update Winter 2016 | Page 6

SITE PROGRESS BRICKWORK has been completed on all outbuildings FINISHING TOUCHES TO THE STEM BUILDING ARE ROOFING FULLY COMPLETE Underfloor heating and screed to Atrium are ongoing and on track ONGOING Stair Hand Rails Work has started on the stairs and is on track Gym SCREEDS COMPLETE Internal glazing to the Atrium is ongoing, as is the internal wall glazing Above: Multi purpose gym Below: Outside the fitness studio and all external electrical services FITNESS room is almost finished, as are the CEILINGS Congratulations to Wayne Taylor for being McLaughlin & Harvey’s Employee of the Month for February