SITE PROGRESS
BRICKWORK
has been completed
on all outbuildings
FINISHING TOUCHES TO
THE STEM BUILDING ARE
ROOFING
FULLY COMPLETE
Underfloor heating and screed to
Atrium are ongoing and on track
ONGOING
Stair Hand Rails
Work has started on
the stairs and
is on track
Gym
SCREEDS COMPLETE
Internal glazing to the
Atrium
is ongoing, as is
the internal
wall glazing
Above: Multi purpose gym
Below: Outside the fitness studio
and all external
electrical services
FITNESS
room is almost finished,
as are the
CEILINGS