Campus Update Autumn 2015 | Page 9

GROUNDWORKS Drainage is being installed including toilets and rainwater drainage. Drains are installed at depths of up to 4m. Further services including electricity, gas and water will follow. POWER A new substation is being constructed at the rear of the new campus on the railway boundary. This will replace the existing sub station on Hill Street. The switch over willl be at the end of November. EXTERIOR Brick work is now complete and two types of cladding are going on: Black PPC and Silver Alucobond. Windows and wall glazing are almost complete. In late September, air handling units were located on roof plant decks. Atrium inverted roof and roof lights are making great progress.