STRUCTURE Partitions are nearly complete and shapes of rooms within the building are almost formed. Mechanical and electrical services are being installed throughout the building as well as a sprinkler system. The suspended ceiling grid installations have begun in the STEM block. Ceiling tiles will soon be inserted enclosing services and leaving a finished surface behind. SHAPE Did you know that the new Kilmarnock Campus is shaped similar to a letter A? STYLE The interior colours of each floor will differ: Ground Floor First Floor Second Floor Third Floor