3rd Bosphorus Bridge. Michel Virlogeux. Izmit Bay Bridge. e-mosty June 2/2016 | Page 45

Erection of Deck The suspended deck segments are erected by lifting devices as shown in below pictures. Obrázek níže ukazuje zdvihání jednotlivých segmentů mostovky. For both installation methods temporary connections were achieved using the matching pieces prepared for both the top and bottom plates to re-establish the deck alignment measured at the trial assembly. The temporary connections prepared on the nose plate took vertical shear force and the top plate took horizontal forces that would occur under wind conditions. The works continued with final welding of the decks, waterproofing and mastic asphalt paving, stone mastic asphalt wearing surfacing and electromechanical installations. The bridge is due to open to traffic by June 2016. U obou metod dočasné styky, tj. lícování v horní i spodní části, znovu vytvořily uspořádání mostovky tak, jak bylo vytvořeno při zkušební montáži. Dočasné styky připravené na čele přenášejí svislé smykové síly, a v horní části přenášejí síly, které by se mohly vyskytnout při zatížení větrem. Práce pokračovaly svařováním mostovky, izolací a pokládáním asfaltového povrchu a elektrickými instalacemi. Otevření mostu pro dopravu je plánováno na červen 2016. 2/2016