Erection of Deck
The suspended deck segments are erected by lifting devices as shown in below pictures.
Obrázek níže ukazuje zdvihání jednotlivých segmentů mostovky.
For both installation methods temporary connections
were achieved using the matching pieces prepared for
both the top and bottom plates to re-establish the
deck alignment measured at the trial assembly. The
temporary connections prepared on the nose plate
took vertical shear force and the top plate took
horizontal forces that would occur under wind
conditions.
The works continued with final welding of the decks,
waterproofing and mastic asphalt paving, stone
mastic asphalt wearing surfacing and electromechanical installations. The bridge is due to open to
traffic by June 2016.
U obou metod dočasné styky, tj. lícování v horní i
spodní části, znovu vytvořily uspořádání mostovky tak,
jak bylo vytvořeno při zkušební montáži. Dočasné
styky připravené na čele přenášejí svislé smykové síly,
a v horní části přenášejí síly, které by se mohly
vyskytnout při zatížení větrem.
Práce pokračovaly svařováním mostovky, izolací a
pokládáním asfaltového povrchu a elektrickými
instalacemi. Otevření mostu pro dopravu je plánováno
na červen 2016.